• School & Neighborhood Safety: Rehabilitation and upgrading of existing school zones with new
signage, pavement markings, flashing beacons; and neighborhood speed awareness/warning
devices to better manage travel speeds in residential areas.
• Street Lighting: Installation of new street lighting in unlighted areas and or rehabilitation of existing
lighting systems including new lighting along the SH26 corridor.
• Traffic Signals: Installation of new traffic signals, system and communication network elements, and
the rehabilitation of existing signals and system components.
Program Summary: Streets
STREETS 2021 2022 2023 2024 2025 Total
Bridges
Pleasant Run Road Bridge at Big Bear $400,000 — — — — $400,000
(White Chapel Bridge) - Construction
Jackson Road Bridge Renovation- — $1,222,302 — — — $1,222,302
Construction
BRIDGES TOTAL $400,000 $1,222,302 $0 $0 $0 $1,622,302
Intersection Improvements
Glade Road at Bluebonnet Drive $1,900,000 — — — — $1,900,000
L.D. Lockett Road Right Turn Ln - $310,000 — — — — $310,000
Construction
INTERSECTION IMPROVEMENTS $2,210,000 $0 $0 $0 $0 $2,210,000
TOTAL
New Construction
SH26 Beautification FY2021 $7,500,000 — — — — $7,500,000
SH26 Beautification FY2022 — $3,000,000 — — — $3,000,000
NEW CONSTRUCTION TOTAL $7,500,000 $3,000,000 $0 $0 $0 $10,500,000
Pavement Markings
Street Pavement Marking-2021 $100,000 — — — — $100,000
Street Pavement Marking-2022 — $100,000 — — — $100,000
Street Pavement Marking-2023 — — $100,000 — — $100,000
Street Pavement Marking-2024 — — — $100,000 — $100,000
Street Pavement Marking-2025 — — — — $100,000 $100,000
PAVEMENT MARKINGS TOTAL $100,000 $100,000 $100,000 $100,000 $100,000 $500,000
Reconstruction
Cheek-Sparger Road (San Bar to $4,105,000 — — — — $4,105,000
Brown Trail) - Construction
Glade Rd (Phase 2-SH26 to Pool)
Design $70,000 — — — — $70,000
Glade Road (Phase 2 - SH26 to Pool) - $9,000,000 — — — — $9,000,000
FY21 Construction