Page 236 - Colleyville FY21 Budget
P. 236

•  School & Neighborhood Safety:  Rehabilitation and upgrading of existing school zones with new
                   signage,  pavement markings, flashing beacons; and  neighborhood speed awareness/warning
                   devices to better manage travel speeds in residential areas.
                •  Street Lighting: Installation of new street lighting in unlighted areas and or rehabilitation of existing
                   lighting systems including new lighting along the SH26 corridor.
                •  Traffic Signals: Installation of new traffic signals, system and communication network elements, and
                   the rehabilitation of existing signals and system components.

              Program Summary: Streets


               STREETS                             2021        2022        2023       2024        2025       Total


               Bridges
               Pleasant Run Road Bridge at Big Bear   $400,000   —          —           —          —         $400,000
               (White Chapel Bridge) - Construction
               Jackson Road Bridge Renovation-      —        $1,222,302     —           —          —       $1,222,302
               Construction
               BRIDGES TOTAL                      $400,000   $1,222,302         $0         $0         $0   $1,622,302

               Intersection Improvements

               Glade Road at Bluebonnet Drive    $1,900,000     —           —           —          —       $1,900,000
               L.D. Lockett Road Right Turn Ln -   $310,000     —           —           —          —         $310,000
               Construction
               INTERSECTION IMPROVEMENTS         $2,210,000         $0          $0         $0         $0   $2,210,000
               TOTAL
               New Construction

               SH26 Beautification FY2021        $7,500,000     —           —           —          —       $7,500,000

               SH26 Beautification FY2022           —        $3,000,000     —           —          —       $3,000,000
               NEW CONSTRUCTION TOTAL            $7,500,000   $3,000,000        $0         $0         $0  $10,500,000
               Pavement Markings

               Street Pavement Marking-2021       $100,000      —           —           —          —         $100,000
               Street Pavement Marking-2022         —          $100,000     —           —          —         $100,000

               Street Pavement Marking-2023         —           —         $100,000      —          —         $100,000

               Street Pavement Marking-2024         —           —           —        $100,000      —         $100,000
               Street Pavement Marking-2025         —           —           —           —        $100,000    $100,000

               PAVEMENT MARKINGS TOTAL            $100,000     $100,000   $100,000   $100,000    $100,000    $500,000

               Reconstruction
               Cheek-Sparger Road (San Bar to    $4,105,000     —           —           —          —       $4,105,000
               Brown Trail) - Construction
               Glade Rd (Phase 2-SH26 to Pool)
               Design                              $70,000      —           —           —          —          $70,000
               Glade Road (Phase 2 - SH26 to Pool) -   $9,000,000   —       —           —          —       $9,000,000
               FY21 Construction