STREETS                             2021        2022        2023       2024        2025       Total

               Pleasant Run Road Rehabilitation   $1,800,000    —           —           —          —       $1,800,000
               (John McCain to N City Limit)
               Water Project 11: Tinker Road
               Water/Drainage/Road               $2,700,000     —           —           —          —       $2,700,000
               Reconstruction
               Glade Road (Phase 2 - SH26 to Pool) -   —     $5,000,000     —           —          —       $5,000,000
               FY22 Construction
               Roberts Road - Construction          —        $1,500,000     —           —          —       $1,500,000

               RECONSTRUCTION TOTAL             $17,675,000   $6,500,000        $0         $0         $0  $24,175,000
               Rehabilitation

               Street Maintenance County-2021     $400,000      —           —           —          —         $400,000

               Street Maintenance Program-2021    $500,000      —           —           —          —         $500,000

               Cooks and Waller Lane                —          $500,000     —           —          —         $500,000
               Hardage Lane                         —          $900,000     —           —          —         $900,000

               Street Maintenance County-2022       —          $400,000     —           —          —         $400,000

               Street Maintenance Program-2022      —          $500,000     —           —          —         $500,000
               Street Maintenance County-2023       —           —         $400,000      —          —         $400,000

               Street Maintenance Program-2023      —           —         $500,000      —          —         $500,000
               Woodbriar/Quail Crest Street
               Rehabilitation (Companion to         —           —        $1,200,000     —          —       $1,200,000
               Wastewater Project 1 and Water
               Projects 6 and 12)
               Street Concrete Panel Replacement-
               2024                                 —           —           —        $750,000      —         $750,000
               Street Maintenance County-2024       —           —           —        $400,000      —         $400,000

               Street Maintenance Program-2024      —           —           —        $500,000      —         $500,000
               Street Concrete Panel Replacement-   —           —           —           —        $750,000    $750,000
               2025
               Street Maintenance County-2025       —           —           —           —        $400,000    $400,000

               Street Maintenance Program-2025      —           —           —           —        $500,000    $500,000

               REHABILITATION TOTAL               $900,000   $2,300,000  $2,100,000  $1,650,000  $1,650,000   $8,600,000
               School and Neighborhood Safety

               Flashing Lights for Pedestrian      $75,000      —           —           —          —          $75,000
               Crosswalks-2021
               Flashing Lights for Pedestrian       —           $75,000     —           —          —          $75,000
               Crosswalks-2022
               SCHOOL AND NEIGHBORHOOD             $75,000    $75,000       $0         $0          $0        $150,000
               SAFETY TOTAL
               STREETS TOTAL                    $28,860,000  $13,197,302  $2,200,000  $1,750,000  $1,750,000  $47,757,302