Page 196 - Saginaw FY20 Annual Budget
P. 196

CITY OF SAGINAW

                          CAPITAL IMPROVEMENT PROJECTS - WASTEWATER
                                                        2019-2023




             Bailey Boswell 12" Sanitary Sewer Extension
             Scope        Jarvis Rd. to Saginaw Blvd.
             Method       Bore and Open Cut
             Project Cost $700,000
             Fiscal Year  Future CIP
                          This project will provide sewer service to new development along Bailey Boswell.  This cost
             Description  estimate assumes construction of the sewer line before or concurrent with the construction of
                          new development.
             Impact on    There will be an eventual increase in maintenance costs as this is a new sewer line.  As the
             Operating    infrastructure ages, estimated annual maintenance cost will be $2,735.
             Budget

             Infiltration/Inflow (I/I) Study Phase 4
             Scope        Big Fossil Creek Basin
             Method       Study
             Project Cost $101,000
             Fiscal Year  Future CIP
                          This study will include flow monitoring and identification of problem sections.  It will also include
             Description  smoke testing and television inspection of selected sections.  The study will recommend
                          projects to address the most critical inflow/infiltration areas.
             Impact on
             Operating    This is a study; there will be no impact on the operating budget until projects are identified.
             Budget