Page 193 - Saginaw FY20 Annual Budget
P. 193

CITY OF SAGINAW

                               CAPITAL IMPROVEMENT PROJECTS - WATER
                                                        2019-2023


              Bailey Boswell Rd 12" Water Line Loop
              Scope        Wagley Robertosn Rd. to Bailey Boswell Rd.
              Method       Open-cut
              Project Cost $575,000
              Fiscal Year  Future CIP
                           This project will provide transmission for distribution lines for development on the
                           undeveloped property on the northeast corner of Bailey Boswell Rd. and Saginaw Blvd.  The
              Description
                           cost estimate assumes construction of the water line before or concurrent with construction
                           of new development.
              Impact on
              Operating    There will be an eventual increase in maintenance costs as this is a new water line.  As the
                           infrastructure ages, estimated annual maintenance cost will be $2,816.
              Budget

              Longhorn Rd. & Old Decatur Rd. 8" Water Line Connection
              Scope        Lansdale Ln. to White Rock Dr.
              Method       Open-cut
              Project Cost $400,000
              Fiscal Year  Future CIP
                           This project will provide additional transmission and looping along Longhrn Rd. and Old
              Description
                           Decatur Rd.
              Impact on
              Operating    There will be an eventual increase in maintenance costs as this is a new water line.  As the
                           infrastructure ages, estimated annual maintenance cost will be $2,563.
              Budget
              FM 156 Utility Relocations
              Scope        Utility relocations for the TxDOT expansion of FM 156
              Method
              Project Cost $415,500
              Fiscal Year  Construction to begin in FY 2019-2020
                           Due to TxDOT widening along FM 156 some utilities will have to be relocated.  The City is
              Description
                           waiting on final plans to determine which lines will need to be relocated.
              Impact on
              Operating    The scope of the project is not known until TxDOT plans are finalized.
              Budget