Page 68 - NRH FY20 Approved Capital Budget
P. 68

Street & Sidewalk Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                                     Street Assessment Project                        ST1902
        Project Description
        The City of North Richland Hills roadway network is comprised of 549 lane miles and this project is for a consultant to utilize
        specialized automated equipment to collect data such as ground penetrating radar, analyze, and process the data in an overall
        pavement assessment. The assessment would yield a digital condition rating system, budget stressing software that allows
        modification of the techniques that would result in a prediction of our current as well as the future condition rating,and create five
        and/or ten year programs that would indicate where funds could be used most impactfully. This project and consultant would be
        slected on an interlocal agreement with the North Central Texas Council of Governments through their 3 vendors previously selected.



        Project Justification
        This assessment will result in a pavement management program that will increase the condition and rideability of our roadway
        network and a  plan for the future to continually see improvement.
        FY 18-19 Funding is proposed from a transfer from Capital Project Fund Reserves.















        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services      10/2018      09/2019   Adopted Budget    2018-19       $140,000
        Engineering/Design                                Total                           $140,000
        Land/ROW Acquisition
        Construction
        Other
        Total Schedule             10/2018      09/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                      140,000           0             0             0      $140,000
        Sales Tax
        Other
        Total Funding                $140,000          $0            $0            $0      $140,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services         140,000           0             0             0      $140,000
        Engineering/Design
        Land/ROW Acquisition
        Construction
        Other
        Total Costs                  $140,000          $0            $0            $0      $140,000
        Operating Impact
        N/A


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0