Page 54 - NRH FY20 Approved Capital Budget
P. 54

Street & Sidewalk Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                                Preventive Street Maintenance (2018)                 SM1801
        Project Description
        This is an annual program where funds are dedicated to enhance the city's efforts for preventive maintenance of city streets.  The
        scope of this project provides crack sealing for approximately 15-25 streets, slurry seals for 15-25 streets and a 2" asphalt overlay
        for 12-15 streets.  In addition to these three maintenance methods, staff will be searching for new preventive procedures to consider
        in the future.






        Project Justification
        Preventive maintenance activities delays more costly street reconstruction and extends the life of the current street system.  This
        project provides staff with funding to apply the appropriate maintenance activities to the streets selected for the program.
        Depending on the current condition of the street and the type of preventive measures taken, the street life can be extended for a
        minimum cost
        in comparison to a total reconstruction.

        Note: Funding is from Certificates of Obligation











        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2017-18      $1,000,000
        Engineering/Design                                Total                          $1,000,000
        Land/ROW Acquisition
        Construction               10/2017      10/2019
        Other
        Total Schedule             10/2017      10/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation  1,000,000           0             0             0     $1,000,000
        Federal/State Grants
        Reserves
        Sales Tax
        Other
        Total Funding               $1,000,000         $0            $0            $0     $1,000,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                1,000,000           0             0             0     $1,000,000
        Other
        Total Costs                 $1,000,000         $0            $0            $0     $1,000,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0