Page 228 - NRH FY20 Approved Capital Budget
P. 228

Facilities Capital Projects
        Department                                             Project Title                         Project Number
        Facilities and Construction                Carpet Replacement at the Public Library               FC2001
        Project Description
        This project consists of replacement of the carpet at the Public Library ($321,000).










        Project Justification
        The carpet at the Public Library is original to construction and is nearing its life expectancy.  The Library has on average 250,000
        visitors each year.  This project would require the stacks to be moved, removal of the old carpet, and replacement with new carpet in
        the public and staff areas.
        Funding source: $320,000 from Certificates of Obligation and $1,000 from  Facility Services Fund (505).














        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Proposed          2019-20       $321,000
        Engineering/Design                                Total                           $321,000
        Land/ROW Acquisition
        Construction               10/2019      09/2020
        Other
        Total Schedule             10/2019      09/2020
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation        0        320,000            0             0      $320,000
        Federal/State Grants
        Reserves                          0          1,000            0             0        $1,000
        Sales Tax
        Other
        Total Funding                     $0       $321,000          $0            $0      $321,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      0        321,000            0             0      $321,000
        Other
        Total Costs                       $0       $321,000          $0            $0      $321,000
        Operating Impact
        No operating impact expected


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             210
   223   224   225   226   227   228   229   230   231   232   233