Page 222 - NRH FY20 Approved Capital Budget
P. 222
Facilities Capital Projects
Department Project Title Project Number
Facilities and Construction City Hall (Municipal Government Complex) FC1205
Project Description
This project is for the design, acquisition, and construction of a new municipal complex up to 183,000 square feet to consolidate
multiple city services and departments into one location. The new City Hall (Municipal Government Complex) will include the
following city services and departments: City Hall, Police Department (including Police Property, Traffic, Crime Scene and SWAT),
Municipal Court, Parks Administration, Citicable, Fire Administration & Emergency Management, and Neighborhood Services. The
proposed 183,000 square feet would be constructed to provide Public Safety operations 93,000 square feet, City Hall 75,000 square
feet, and Municipal Court 15,000 square feet. The square feet dimensions by function could be redefined during the design process.
Project Justification
The existing location of city services and departments have been impacted by the widening of Loop 820. City Hall, Police
Department, Municipal Court, and Parks Administration available parking has been substantially reduced to less available parking
spaces. The result of the reduced parking and landscaping at Parks Administration and Municipal Court impacted the fire lanes
located in the front of the building. There is no longer adequate space in front of the building for required emergency responder
access. The fire lanes at City Hall and the Police Department need to be reconfigured, which will result in additional parking being
lost. Due to the widening of Loop 820 both locations are non-compliant with several codes and government regulations.
The new City Hall (Municipal Government Complex) will allow the City to position multiple City services and departments into one
conducive location for the Residents, Employees, and Visitors of North Richland Hills.
Project cost is estimated to be $69,284,287. Funding sources consist of $48,000,000 in G.O. Bonds issuance, $250,000 in G.O
Bond issuance from the 2003 bond election for the EOC, $18,600,000 in Certificates of Obligation issuance. $2,434,287 in "Other"
will be financed by PEG funds, Court Technology Funds, Special Investigations Funds, Traffic Safety Funds, 9-1-1 Communication
Assistance Funding, Gas Development, and other reserves. Reserves in the amount of $2,126,428 are from the sale of the old City
Hall.
Project Schedule Beginning Date Ending Date History Fiscal Year Amount
Professional Services 07/2012 11/2017 Adopted Budget 2011-12 $70,000,000
Engineering/Design 07/2012 11/2017 Revision 2013-14 ($770,663)
Land/ROW Acquisition 06/2012 08/2017 Revision 2015-16 $54,950
Construction 12/2013 11/2018 Revision 2018-19 $2,126,428
Other Total $71,410,715
Total Schedule 06/2012 11/2018
Sources of Funds To Date 2019-20 Budget 2020-21 Estimate 2021-Completion Total Funding
General Obligation Bonds 48,250,000 0 0 0 $48,250,000
Certificates of Obligation 18,600,000 0 0 0 $18,600,000
Federal/State Grants
Reserves 2,126,428 0 0 0 $2,126,428
Sales Tax
Other 2,434,287 0 0 0 $2,434,287
Total Funding $71,410,715 $0 $0 $0 $71,410,715
Project Costs To Date 2019-20 Budget 2020-21 Estimate 2021-Completion Total Cost
Professional Services 4,944,197 0 0 0 $4,944,197
Engineering/Design 282,000 0 0 0 $282,000
Land/ROW Acquisition 162,785 0 0 0 $162,785
Construction 58,700,706 0 0 0 $58,700,706
Other 7,321,027 0 0 0 $7,321,027
Total Costs $71,410,715 $0 $0 $0 $71,410,715
Operating Impact
Operating impact will be added after Consultants are hired and provided a Performa on estimated expenditures.
Fiscal Year 2019-20 2020-21 2021-22 2022-23 2023-24 Total Impact
Amount $0 $0 $0 $0 $0 $0
Total Operating Impact $0 $0 $0 $0 $0 $0