Page 133 - NRH FY20 Approved Capital Budget
P. 133

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                                 Main / Snider / Center Utility Project               UT1902
        Project Description
        The project consists of engineering and construction of water and sanitary sewer main extensions to provide service to properties
        north and south of Main Street off of Snider Street and Center Street in the TOD.









        Project Justification
        Grant funds are available to facilitate paving and streetscape improvements in the Main / Snider / Center area in the vicinity of the
        Smithfield Rail Station in the City's Transit Oriented Development (TOD) zoning district.  The grant funds do not include provisions
        for water and sanitary sewer facilities, which must be located under the street in order to allow for the street lights and street trees in
        the parkways as required in the TOD.  As such, the utilities will need to be installed prior to the paving work, and paid for with City
        funds. This upgrade is required to accommodate multi-family and commercial development plans in this area.














        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2018-19       $225,000
        Engineering/Design         10/2018      02/2019   Total                           $225,000
        Land/ROW Acquisition
        Construction               03/2019      08/2019
        Other
        Total Schedule             10/2018      08/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation    225,000           0             0             0      $225,000
        Federal/State Grants
        Reserves
        Sales Tax
        Other
        Total Funding                $225,000          $0            $0            $0      $225,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design            45,000            0             0             0       $45,000
        Land/ROW Acquisition
        Construction                  180,000           0             0             0      $180,000
        Other
        Total Costs                  $225,000          $0            $0            $0      $225,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0