Page 138 - NRH FY20 Approved Capital Budget
P. 138

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                        Sanitary Sewer System Rehabilitation (Various Locations)      UT1703
        Project Description
        This project will consist of replacing approximately 1,200 linear feet of sanitary sewer main lines in North Richland Hills. In addition
        five manholes will be replaced. Streets included in this project will be Nancy Lane (4900 to 5000 block);  8020 Laura Street to 8017
        Lazy Street; and 7000 to 7028 Smithfield Road.







        Project Justification
        In 2010, the City conducted a Sanitary Sewer Assessment for the southern portion of the City (Project UT0902). The Study found
        that approximately 9,000 linear feet of sanitary sewer main lines are in need of replacement. The main lines are made of vitrified
        clay tile and have deteriorated to a point where pipe failures have occurred causing blockage and overflows. Many of the joint pipe
        sections are separated, allowing ground water and surface water intrusion resulting in capacity issues and added costs for the
        treatment of wastewater.

        This project will replace segments of the main lines by using the latest technology such as pipe bursting to eliminate the problem
        lines. The construction methods used will create minor inconveniences to residents. The result will be a more efficient, and safer
        sanitary sewer system in the southern portion of the City.  Approximately 1,200 linear feet of sanitary sewer lines will be replaced or
        repaired with this project.


        Funding source: Utility Operations for Capital Projects.



        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2016-17       $150,000
        Engineering/Design                                Total                           $150,000
        Land/ROW Acquisition
        Construction               10/2016      09/2019
        Other
        Total Schedule             10/2016      09/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                      150,000           0             0             0      $150,000
        Sales Tax
        Other
        Total Funding                $150,000          $0            $0            $0      $150,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                  150,000           0             0             0      $150,000
        Other
        Total Costs                  $150,000          $0            $0            $0      $150,000
        Operating Impact
        No impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0