Page 122 - Grapevine FY20 Approved Budget
P. 122

Public Works - Engineering
                                                       100-415-002




                   Expenditures by                  2016-17    2017-18    2018-19   2018-19    2019-20
                   Major Object                      Actual     Actual    Budget    Estimate  Approved
                   Personnel Services                740,344   835,641    879,327   875,657    914,508
                   Supplies                          15,797     16,003     10,100    11,408     12,000
                   Maintenance                           0          0          0       545          0
                   Services                          17,071     23,602     31,500    21,939     30,000

                   Total                             773,211   875,246    920,927   909,549    956,508

                   Objectives

                     Minimize response time for the public and respond to requests for information in a timely manner.
                     Development
                     Review plat submittals promptly to provide responsive service to the property owner/developer.
                     Conduct private development plan review in a timely manner


                     Capital Projects
                     Develop Capital Improvement projects through detailed construction review plans and meeting project design
                     schedules.
                     Ensure that CIP projects remain within allocated funding through detailed budget preparation, payment review,
                     cost projection and records maintenance.

                     Construction Inspection
                     Ensure quality construction, reduce future maintenance costs, and maintain construction schedules of both CIP
                     and private development projects through dedicated inspection and construction management.
                     Provide construction administration services to City Bond building projects



                                                    2016-17    2017-18    2018-19   2018-19    2019-20
                   Performance Indicators            Actual     Actual    Budget    Estimate  Approved

                   Development
                   Develop partnerships with private    NA        NA         NA         NA          2
                   developers to levage funding
                   Pavement constructed (square yards)  14,205  14,205     15,000    15,000     15,000
                   Water line constructed (linear feet)  25,504  25,504    10,000    10,000     10,000
                   Wastewater line constructed (linear feet)  5,688  5,688  10,000   10,000     10,000
                   Storm drain line constructed (linear feet)  14,003  14,003  8,000  8,000      2,000
                   Plats processed                       16        16         30        30         30

                   Capital Projects
                   Design contracts awarded (water,      1          1          4         4          5
                   wastewater & drainage_)
                   WTP Rehab / Update Projects           2          2          2         2          2
                   WWTP Rehab / Update Projects          3          3          2         2          2
                   Elevated Storage Tank Rehab / Update  0          0          2         2          1
                   Lift Station Upgrades                 0          0          1         1          1

                   Construction Inspections
                   Lot to Lot Drainage Inspections      NA        NA         NA         NA        400
                   Public Buildings under construction  NA        NA         NA         NA          6



                                                          114
   117   118   119   120   121   122   123   124   125   126   127