Sidewalks/Trails
Sidewalk/trail improvements encompass the installation of new sidewalk/trail segments, removal of
obstructions along existing segments, and improvements to access ramps to ensure compliance with
accessibility standards. Sidewalk/trail improvements are targeted to improve pedestrian mobility and
access around schools, recreation areas, community centers, and other high pedestrian uses.
Program Summary: Sidewalks/Trails
Sidewalks/Trails 2020 2021 2022 2023 2024 Total
New Construction
Annual Sidewalk/Trail — — — — $500,000
Construction/Grant Match FY2020 $500,000
Bransford Rd Trail (Field St to Cotton — — — — $50,000
Belt Trail)-Design $50,000
John McCain Road Trail - Design $50,000 — — — — $50,000
John McCain Road Trail - Construction $800,000 — — — — $800,000
Annual Sidewalk/Trail — — — — $500,000
Construction/Grant Match FY2021 $500,000
Bransford Rd Trail (Field St to Cotton — — — — $800,000
Belt Trail)-Construction $800,000
Annual Sidewalk/Trail — — — — $500,000
Construction/Grant Match FY2022 $500,000
Annual Sidewalk/Trail — — — — $500,000
Construction/Grant Match FY2023 $500,000
Annual Sidewalk/Trail — — — — $500,000
Construction/Grant Match FY2024 $500,000
New Construction Total $1,400,000 $1,300,000 $500,000 $500,000 $500,000 $4,200,000
Rehabilitation
— — — — $400,000
Cheek-Sparger Trail $400,000
— — — — $400,000
Misc Concrete Rehabilitation FY2020 $400,000
— — — — $400,000
Misc Concrete Rehabilitation FY2021 $400,000
— — — — $400,000
Misc Concrete Rehabilitation FY2022 $400,000
— — — — $400,000
Misc Concrete Rehabilitation FY2023 $400,000
— — — — $400,000
Misc Concrete Rehabilitation FY2024 $400,000
Rehabilitation Total $800,000 $400,000 $400,000 $400,000 $400,000 $2,400,000
Sidewalks/Trails Total $2,200,000 $1,700,000 $900,000 $900,000 $900,000 $6,600,000