Page 226 - FY2020Colleyville
P. 226

Program Summary: Water

               WATER                               2020        2021      2022       2023       2024       Total

               Water Renewals
               L.D. Lockett Pump Station Emergency   $650,000   —          —          —         —        $650,000
               Generator
               Pleasant Run Waterline (John McCain   $800,000   —          —          —         —        $800,000
               North to Bear Creek) - Construction
               Pleasant Run Waterline Vault -     $375,000      —          —          —         —        $375,000
               Construction
               Supervisory Control and Data       $350,000      —          —          —         —        $350,000
               Acquisition (SCADA) Replacement
               Water Project 11: Tinker Road Water   $123,000   —          —          —         —        $123,000
               Lines - Design
               Bransford Water Tank Rehabilitation -   —    $1,200,000     —          —         —       $1,200,000
               Construction
               Water Project 10: Apple Valley/Rustic
               Oaks/Bills Lane Water Lines and Road   —       $630,000     —          —         —        $630,000
               Rehabilitation on Black Drive and
               Rustic Trail
               Water Project 11: (Partial) Tinker   —       $1,110,000     —          —         —       $1,110,000
               Road Water Lines - Construction
               Water Project 7: Demolish Overland   —         $250,000     —          —         —        $250,000
               Trail Pump Station
               Water Project 12: (Partial) Woodbriar
               Estate Water Lines Replacement -     —           —        $70,020      —         —         $70,020
               Design
               Water Project 5: Upsize and Replace
               Water Lines in Brighton Oaks         —           —       $145,000      —         —        $145,000
               Subdivision and Rehabilitate Streets -
               Design
               Water Project 6:  Upsize and Replace
               Water Lines in Woodbriar Estates and   —         —       $145,000      —         —        $145,000
               Quail Crest Subdivisions - Design
               Water Project 12: Partial Woodbriar
               Estate Water Lines Replacement -     —           —          —       $433,000     —        $433,000
               Construction
               Water Project 5: Upsize and Replace
               Water Lines in Brighton Oaks         —           —          —      $2,550,000    —       $2,550,000
               Subdivision and Rehabilitate Streets -
               Construction
               Water Project 6: Upsize and Replace
               Water Lines in Woodbriar Estates and   —         —          —       $745,000     —        $745,000
               Quail Crest Subdivisions -
               Construction
               WATER TOTAL                       $2,298,000  $3,190,000   $360,020  $3,728,000     $0  $9,576,020


              Exhibits

                   A.  Fiscal Year 2020 Individual Project Pages
                   B.  Fund Balance
                   C.  5 Year Capital Improvement Plan FY2020-2024 - Project List