 Capital Improvement Plan
 2018-2022

 USE OF FUNDS                                                           SOURCE OF FUNDS
 Actual  Revised                     Tarrant     Cap Proj     General     Escrow      Donations  Enterprise   Drainage      To Be
 Project Description  Note Prior Years 2017-2018  2018-2019  2019-2020  2020-2021  2021-2022  Future CIP  Total  County  Fund  Fund  Fund  Fund  Fund  Fund  Determined
 South Hampshire 16" Water Line  1,3  35,000  692,000  0  727,000          706,000                  21,000                          0
 South Hampshire across Hialeah Park to Saginaw Blvd
 Saginaw Blvd 12" Water Line Ph. 1  3  529,497  529,497                    529,497                                                  0
 McLeroy to Palomino
 Saginaw Blvd 12" Water Line Ph. 2  3  40,000  322,000  362,000            362,000                                                  0
 200 feet south of Palomino Dr. to Hialeah Park St.
 Park Center Elevated Storage Tank Rehabilitation  1  1,200,000  1,200,000                       1,200,000                          0

 West McLeroy 12" Water Line Ph. 2  5        280,600  0  280,600           280,600                                                  0
 Elementary #14 to Old Decatur Rd.
 Lawson and Watson 8" Water Line  1  404,334  404,334                                              404,334
 along Lawson Rd and S Watson Rd
 East McLeroy 12" Water Line  5  550,000  550,000                                                                            550,000
 S-Curve to Blue Mound Road
 Basswood Blvd. 12" Water Line  5  540,000  540,000                                                                          540,000
 Bailey Boswell Rd. to TXU Easement
 Old Decatur 8" Water Line  5  290,000  290,000                                                                              290,000
 West McLeroy Blvd. To Springhill Dr.
 Old Decatur 12" Water Line Ph. 1  5        260,000  260,000                                                                 260,000
 West McLeroy Blvd. to First Baptist Church
 Bailey Boswell Water Line Relocation Ph.2 & 3  1  733,365  0  733,365                             733,365                          0
 4,750 LF from Saginaw Blvd. to Jarvis Rd.
 Saginaw Blvd 16" Water Line Ph.2  3  155,000  1,066,050  0  1,221,050   1,221,050                                                  0
 Palomino across Saginaw Blvd to Samson 12" water line
 FM. 156 12" Water Line  6  186,511  0  186,511                            118,065                  68,446                          0
 Grand Central Parkway to north of Highland Stn Trl
 Heather Ridge Pkwy 12" Water Line  5  420,000  420,000                                                                      420,000
 2,498 LF; Heather Ridge Pkwy to Basswood Blvd
 FM. 156 12" Water Line Phase 2  5  370,000  370,000                                                                         370,000
 1,971 LF; 450' north of Topeka Dr to BB Rd
 Condor Trl 12" Water Line  5  540,000  540,000                                                                              540,000
 3,262 LF; Condor Trl to BB Rd
 Defiel Rd 8" Water Line  5  510,000  510,000                                                                                510,000
 2,396 LF; Defiel Rd cul-de-sac to BB Rd
 Bailey Boswell Rd 12" Water Line Loop  5  520,000  520,000                                                                  520,000
 2,916 LF; Wagley Robertson Rd to BB Rd
 Longhorn Rd & Old Decatur 8" Water Line Connection  5  340,000  340,000                                                     340,000
 1,258 LF; Landsdale Ln to White Rock Dr
 FM 156 Utility Relocations  1     874,000  0  874,000                                             874,000                          0

 Total Water System  1,928,707  2,214,000  1,029,000  1,066,050  280,600  0  4,340,000  10,858,357  0  0  0 3,217,212  0 3,301,145  0  4,340,000


 Notes
 1 Project funded through cash reserves
 2 Includes two (2) grant applications to Texas Parks and Wildlife Department
 3 Project funded through Utility Impact Fees
 4 Projects constructed by City of Fort Worth
 5 Projects possible constructed by Developers
 6 Utility Relocation Project for TXDOT Highway Expansion
 7 Paid with Drainage Utility Reserves
 8 Paid with Cap Proj Reserves and Drainage Utility Fund
 9 Paid with Drainage Utility Fees
 10 On hold due to TXDOT Review Fee Issue






























 174
   171   172   173   174   175   176   177   178   179   180   181