Page 174 - Saginaw FY19 Annual Budget
P. 174

City of Saginaw
 Capital Improvement Plan
 2018-2022

 USE OF FUNDS                                                           SOURCE OF FUNDS
 Actual  Revised                     Tarrant     Cap Proj     General     Escrow      Donations  Enterprise   Drainage      To Be
 Project Description  Note Prior Years 2017-2018  2018-2019  2019-2020  2020-2021  2021-2022  Future CIP  Total  County  Fund  Fund  Fund  Fund  Fund  Fund  Determined
 Western Center/156 Paving Improvements and Signal Design  1  389,114  389,114  389,114
 Bailey Boswell Ph. 1 Reconstruction  3,314,986  3,314,986  1,664,986  1,650,000                                                    0
 Old Decatur Rd to Saginaw Blvd
 Bailey Boswell Preliminary Design  911,773  7,620  919,393  919,393
 All Phases - Phase 2 through Overpass
 Bailey Boswell Overpass  414,247  29,530  3,350,000  8,740,000  0  12,533,777  4,000,000  8,533,777                                0
 Bailey Boswell from Saginaw Blvd to the S-curve
 Bailey Boswell Ph. 2 Reconstruction  6,515,331  6,335,075       0  12,850,406  12,117,041         733,365                          0
 Saginaw Blvd to Jarvis Road
 Bailey Boswell Ph. 3 Reconstruction
 Jarvis Road to Approx. 500' west of Ash Meadow Dr.
 Bailey Boswell Ph. 4 Reconstruction  4,073,745  0       0  4,073,745  3,866,745  207,000                                           0
 Approx. 500' west of Ash Meadow Dr. to FM 156
 E. McLeroy Boulevard (Western Center Extension)  4,100,000  4,100,000                                                      4,100,000
 S-curve to Blue Mound Rd
 E. McLeroy Boulevard Ph. 2 Reconstruction  10,400,000  10,400,000                                                        10,400,000
 S-curve to Saginaw Blvd
 W. McLeroy Boulevard Ph. 3 Reconstruction  8,500,000  8,500,000                                                            8,500,000
 Saginaw Blvd to Knowles Dr.
 W. McLeroy Boulevard Ph. 4 Reconstruction  5,200,000  5,200,000                                                            5,200,000
 Knowles Dr. to Old Decatur Rd
 Knowles Drive Ph. 1 Reconstruction to 3 lanes  3,400,000  3,400,000                                                        3,400,000
 Longhorn Rd. to McLeroy Blvd
 Knowles Drive Ph. 2a Reconstruction to 3 lanes  2,500,000  2,500,000                                                       2,500,000
 W. McLeroy Blvd to Woodcrest Dr.
 Knowles Drive Ph. 2b Reconstruction to 3 lanes & Drainage  4,290,000  4,290,000                                            4,290,000
 Woodcrest Dr. to WJ Boaz Rd.
 Knowles Drive Ph. 3 Reconstruction  1,220,000  1,220,000                                                                   1,220,000
 W.J. Boaz Rd to Normandy Ln
 Industrial Blvd Reconstruction  5,400,000  5,400,000                                                                       5,400,000
 10,000' East of Saginaw Blvd to FM 156
 W.J. Boaz  850,000       850,000                                                                                            850,000
 Old Decatur Rd to Knowles Dr
 Heather Ridge Pkwy Extension  1,000,000  1,000,000                                                                         1,000,000
 400' North of Raven Dr. to Woodcrest Development
 Basswood Blvd (Whistle Stop Dr. to BB)  490,000  0  490,000   164,250      57,750                             268,000              0
 2 lanes for 1,100 ft and 4 lanes for 1,700 ft
 Old Decatur Road North  1,800,000  1,800,000                                                                               1,800,000
 Bailey Boswell north to city limits
 Railroad Quiet Zone Study  60,000  60,000                                                                                    60,000
 Total Street Construction  15,619,196  6,862,225  3,350,000  8,740,000  48,720,000  83,291,421 5,664,986 27,086,956  553,364  264,750  0  733,365  268,000  48,720,000

 Americans with Disabilities Act Transition Plan     48,000  33,000  32,000  50,000  50,000  70,000  70,000  353,000  113,000  240,000
 Park Master Plan  1,2  35,000  30,500     65,500               65,500                                                              0
 Park Master Plan Projects  1  276,609  50,000  0  0  326,609  166,609      50,000     110,000                                      0
 Public Works Facility  35,615  unknown  35,615                 17,808                              17,808                          0
 Softball/Baseball Complex      0                                                                                                   0
 Recreation Center Expansion    0                                                                                                   0
 Fire Station #1 Drainage Improvements  0                                                                                           0
 Library Expansion/Satellite Annex  0                                                                                               0
 Total Community Facilities  395,224  83,000  62,500  50,000  50,000  70,000  70,000  780,724  0  0  362,917  50,000  110,000  17,808  0  240,000


 Notes
 1 Project funded through cash reserves
 2 Includes two (2) grant applications to Texas Parks and Wildlife Department
 3 Project funded through Utility Impact Fees
 4 Projects constructed by City of Fort Worth
 5 Projects possible constructed by Developers
 6 Utility Relocation Project for TXDOT Highway Expansion
 7 Paid with Drainage Utility Reserves
 8 Paid with Cap Proj Reserves and Drainage Utility Fund
 9 Paid with Drainage Utility Fees
 10 On hold due to TXDOT Review Fee Issue