Page 449 - City of Arlington FY19 Adopted Operating Budget
P. 449

Public Safety



                             Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
                         Objective 1: Plan and implement stormwater projects to mitigate or minimize flood risks
                         Project                   Performance Measure(s)         City Service Team (Department)
             Core   Flood Mitigation Buyouts                                   Economic Development and Capital
             PS                                                                Investment (PWT)
             2.1.2
             Summary:

             An ongoing flood mitigation buyout program is
             instrumental in the City’s flood protection program.    House   Appraisal   Purchase   Closed
             In many cases, it is impossible to prevent flooding of       Received    Agreement
             homes adjacent to creeks with construction projects.    1   Aug. 2017    Sept. 2017   Oct. 2017
             In these cases, purchasing and demolishing the     2        Aug. 2017    NA         NA
             homes is the only way to prevent future flooding.    3      Aug. 2017    Jan. 2018   June 2018
             This is a voluntary program and homes purchased are   4     Aug. 2017    NA         NA
             those that have repetitively flooded.              5        Aug. 2017    Oct. 2017   Nov. 2017
                                                                6        Aug. 2017    Oct. 2017   Jan. 2018
             In September 2017, the City received a grant from   7       Apr. 2017    May. 2017   July 2017
             FEMA for the purchase of 6 homes.  The grant
                                                                8        Feb. 2017    June 2017   Oct. 2017
             requires that all homes be purchased and           9        May 2017     June 2017   Oct. 2017
             demolished by September 2018.  In addition to the
             grant‐funded purchases, three additional homes will
             be purchased with city funds.                             House    Asbestos     Demo
                                                                                 Survey
             Update:
             The demolition and abatement contract was                 1       Dec. 2017   Pending
                                        th
             approved by Council on August 7 .  Abatement and          2       NA          NA
                                                                       3       Apr. 2018   Oct. 2018
             demolition of houses 3, 5, 6, 8, and 9 started in
             September.  Demolition tasks of these houses will be      4       NA          NA
             completed in October, weather permitting.                 5       Nov. 2017   Oct. 2018
             Abatement and demolition of houses 1 and 7 delayed        6       Apr. 2018   Oct. 2018
             due to weather. Demolition of these houses                7       Sept. 2017   Pending
             expected to be completed in November, weather             8       Oct. 2017   Oct. 2018
             permitting.                                               9       Oct. 2017   Oct. 2018