                             Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
                         Objective 1: Plan and implement stormwater projects to mitigate or minimize flood risks
                         Project                   Performance Measure(s)         City Service Team (Department)
             Core   Stormwater Projects      Implement projects that mitigate   Economic Development and Capital
             PS                              flooding concerns                 Investment (PWT)
             2.1.1
             Summary:

             Stormwater Projects are funded through the
             Stormwater Utility Fee and are included in the annual
             capital budget.  The projects listed below are
             expected to begin or complete construction during
             FY 2018. Project milestones listed in the table will be
             updated as they occur during the year.

             Update:
             The Wimbledon and the Greencove Drainage
             Projects are proceeding on schedule.  The
             Washington Erosion and Country Club Drainage
             Projects are slightly delayed so that necessary
             acquisitions were able to be completed.  The Sublett
             Creek Drainage Improvements were on hold until
             homes in the project area that were previously
             acquired had been demolished but will now proceed.



                                   Project                       Estimated   Actual Bid   Estimated   Actual
                                                                 Bid Dates    Dates     Completion   Completion
              North Fork Cottonwood Creek Channel Repair       Oct. 2017    Apr. 2017   Feb. 2018   Feb. 2018
              Rush Creek at Bowen Erosion and Scour Repair     Nov. 2017    May 2017   Nov. 2017    Oct. 2017
              Meadow Park Drainage Improvements                June 2017    June 2017   May 2018    Apr. 2018
              Sublett Creek Neighborhood Drainage Improvements   June 2018
              Greencove Drainage Improvements                  Apr. 2018    Apr. 2018   Feb. 2019
              Wimbledon Drainage Improvements                  Apr. 2018    Apr. 2018   Jan. 2019
              JC‐9 Erosion Repair                              May 2018     July 2018   Jan. 2019
              Washington Erosion Project                       Sept. 2018
              Country Club Drainage Improvements               Sept. 2018



















                                                             117