Page 448 - City of Arlington FY19 Adopted Operating Budget
P. 448
Public Safety
Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
Objective 1: Plan and implement stormwater projects to mitigate or minimize flood risks
Project Performance Measure(s) City Service Team (Department)
Core Stormwater Projects Implement projects that mitigate Economic Development and Capital
PS flooding concerns Investment (PWT)
2.1.1
Summary:
Stormwater Projects are funded through the
Stormwater Utility Fee and are included in the annual
capital budget. The projects listed below are
expected to begin or complete construction during
FY 2018. Project milestones listed in the table will be
updated as they occur during the year.
Update:
The Wimbledon and the Greencove Drainage
Projects are proceeding on schedule. The
Washington Erosion and Country Club Drainage
Projects are slightly delayed so that necessary
acquisitions were able to be completed. The Sublett
Creek Drainage Improvements were on hold until
homes in the project area that were previously
acquired had been demolished but will now proceed.
Project Estimated Actual Bid Estimated Actual
Bid Dates Dates Completion Completion
North Fork Cottonwood Creek Channel Repair Oct. 2017 Apr. 2017 Feb. 2018 Feb. 2018
Rush Creek at Bowen Erosion and Scour Repair Nov. 2017 May 2017 Nov. 2017 Oct. 2017
Meadow Park Drainage Improvements June 2017 June 2017 May 2018 Apr. 2018
Sublett Creek Neighborhood Drainage Improvements June 2018
Greencove Drainage Improvements Apr. 2018 Apr. 2018 Feb. 2019
Wimbledon Drainage Improvements Apr. 2018 Apr. 2018 Jan. 2019
JC‐9 Erosion Repair May 2018 July 2018 Jan. 2019
Washington Erosion Project Sept. 2018
Country Club Drainage Improvements Sept. 2018
117