5 Year Projects, Time-Phased Plan 2023-2030 and beyond
Street/Water/Sewer Improvement Projects
Street Name Length Width Description Street Water Sewer Completed 2023 2024 2025 2026 2027 2028 2029 2030
Bowling Green St. & Brambleton Pl.
1,050 30 Crawford Ln. to Nell St. $139,000.00 $230,000.00 street/water
Brambleton Pl.
4,000 Truett St. to Nell; mill & overay $250,000.00
Bowling Green
1,200 4100/4200 block; mill & overlay $100,000.00
Alandale Dr. 560 30 Wanda Ln. to Scotsdale Dr. $120,000.00 water
(Trailwood Dr.) - Forest Hill Cir. to
Trailwood Dr./Woody Ln./Woodview Ln. 2,500 30 Parkwood Dr.; (Woody/Woodview)-
Anglin Dr. to Trailwood Dr. $580,370.00 DONE street
Forest Hill Dr. 3,400 40 Mansfield Hwy. to Lon Stephenson $1,000,000.00 street
Rd.; repair damaged concrete
Grady St. 1,960 30 Forest Hill Dr. to Wichita St. $160,000.00 DONE street $160,000.00
Dorsey St. to Leonard St.;
Griggs St. 1,200 30 reconstruction $92,400.00 DONE street $92,400.00
Truett St. 2,262 30 Cardinal Ridge to Orchard St. $220,000.00 DONE $370,000.00 street/water
Story St. 800 30 Truett St. to Forest Hill Dr., Truett St. $80,000.00 DONE $75,200.00 street/water/ $80,000.00
to Crawford Ln., mill work
sewer
Wanda Ln. 3,500 30 Marshall St. to Leonard St., overlay $269,500.00 DONE street/water
Forest Hill Circle to Koldin Trail;
Nauret Rd. 1,300 30 overlay $120,000.00 DONE street
Salem Ct. 560 Curb & gutter; damaged prior project $40,000.00 DONE
Salem Ct. 560 Reconstruction $120,000.00 $180,000.00 $240,000.00
Hartman Rd. to Shady Hill Dr.;
Leonard St. overlay $49,408.00 DONE street $49,408.00
Leonard St. Sewer $500,000.00
George Ave. 1,200 Forest Hill Dr. to Wichita St.; overlay $130,000.00 street $130,000.00
George Ave. 1,200 $300,000.00
Shady Hill Lane N 820 30 I20 to Cul-De-Sac $140,000.00 DONE $170,000.00 street/water
Shady Hill Lane N 820 30 I20 to Cul-De-Sac $170,000.00 $300,000.00
Shady Hill Lane E/W 1,000 Wanda Ln. to Leonard $280,000.00
Woodbridge Dr.
*48th CDBG funding= $211,691 2,173 30 Forest Hill Dr. to Folkstone Dr.
$276,530.00 water $65,000.00
Woodbridge Dr. *CDBG CARES ACT 595 3500 & 7300 block of Woodbridge
funding=$178,869 $178,869.00 $0.00
Woodbridge Dr.
*50th Yr. CDBG funding =$130,000 645 7300 blk Woodbridge, s of Lee St.
$130,000.00
Woodbridge Dr -remaining *52nd Year
CDBG Funding 300
TBD
Falmouth Drive 1,170 $1,188,639
*ARPA Funding 30 Woodbridge Dr. to Chimney Rock Dr. (includes sewer) DONE *included $260,000.00
$997,600
Alandale Dr. *ARPA Funding 560 30 Marshall St. to Anglin Dr. (includes sewer) *included
Oak Crest Drive West 480 30 IH20 to Mansfield Hwy. $200,000.00 $60,000.00
Nantucket (PW to complete) 200 $60,000.00 $60,000.00