PROJECT  TITLE:    RECLAIMED  WATER   LINE EXT.  PHASE  III        PROJECT  CODE:   WT1604

             NET EFFECTS  ON OPERATING   AND                 TOTAL  ESTIMATED  CAPITAL  COST:
             MAINTENANCE   COST (+  OR -)  ANNUAL:
                                                              Engineering                               662, 232
             Direct  Operating  Cost                         Construction                              5, 414, 672
             Personnel:         Full Time                     Loan Origination  Fee                      47, 899
                                Part Time
             Total Salary                                   0
             Purchase  of Services
             Materials &  Supplies
             Utilities

             2018 Rev Bond Avg.  Annual DS            160, 000
             2015B Rev Bond Avg.  Annual DS ( 50%)     70, 000
             Subtotal:                                230, 000 Total Estimated  Capital  Cost          6, 124, 803

                                                              FUNDING  SOURCE:
             Maintenance  Costs
                                                             Transfer from WT1212:
                                                             2015B  Revenue  Bond  Issue               1, 192, 103
                                                             W/ WW CIP Fund  Balance                     75, 093

                                                             2018 Revenue  Bond Issue                  2, 785, 000
                                                              Loan  Forgiveness                         473, 300
                                                            0 Interest Earnings                         124, 709
             Subtotal:                                      0 W/ WW Operating Fund                     1, 000, 000
                                                              Rate Stabilization                        500, 000
                                                             Transfer  to:
                                                             W/ WW CIP Fund Balance                      25, 402)
             Total  Estimated  Annual  Cost           230, 000 Total Funding                           6, 124, 803
                                                    CURRENT    STATUS

                                                                                 OVER/ UNDER
             PHASE/ FUNDING  SOURCE               BUDGET         EXPENDED         BUDGET (- +)      EXPENDED
             Engineering                             662, 232           662, 232             0)            100%
             Construction                           5, 414, 672       3, 914, 672     1, 500, 000           72%
             Loan Origination  Fee                    47, 899            47, 899             0             100%
























             TOTAL PROJECT                          6, 124, 803       4, 624, 803     1, 500, 000           76%