CITY OF EULESS
CAPITAL IMPROVEMENT PROGRAM
AMENDMENTS -- FUNDED PROJECTS
PROJECT# PROJECT DESCRIPTION DATE AMENDMENTS & ACTIONS
WT1403 Reclaimed Water Line Extension Debt Payment— Impact 10/ 01/ 2024 To provide additional funding per FY2025 Approved CIP Plan — $ 120,050
from Water Impact Fee Fund Balance.
WT1603 Miscellaneous Valve Replacement 10/ 01/ 2024 To provide additional funding per FY2025 Approved CIP Plan — $ 50, 000
from W/ WW CIP Fund Balance.
WT1802 Well Replacement— Fuller/ Far North 05/ 31/ 2025 To decrease budget by $ 3, 754 for arbitrage payment.
WT2501 Line Replacement— Sotogrande Boulevard Phase II 10/ 01/ 2024 To provide funding per FY2025 Approved CIP Plan — $ 365,000 from
W/ WW Operating Fund.
WW0002 Miscellaneous Wastewater Rehabilitation 10/ 01/ 2024 To provide additional funding per FY2025 Approved CIP Plan — $ 100,000
from W/ WW CIP Fund Balance.
WW0605 TRA Wastewater Payments — Impact 10/ 01/ 2024 To provide additional funding per FY2025 Approved CIP Plan — $ 50, 000
from WW Impact Fee Fund Balance.
WW2501 FY2025 51st CDBG LR: Fair Oaks Boulevard/ Lone Oak Circle 10/ 01/ 2024 To provide funding per FY2025 Approved CIP Plan — $ 292, 000 from
Community Development Block Grant.
WW2501 FY2025 51st CDBG LR: Milam Drive 02/ 25/ 2025 To provide additional funding of $ 8, 750 from Community Development
Block Grant. Project selection switched from Fair Oaks Boulevard/ Lone
Oak Circle to Milam Drive due to map eligibility changes.
WW2502 Line Replacement — Oakwood Terrace North Phases I, II, & III 10/ 01/ 2024 To provide funding per FY2025 Approved CIP Plan — $ 309, 000 from
Engineering W/ WW Operating Fund.
Ordinance No. 2432, Page 158 of 474