Page 163 - CityofEulessFY26AdoptedBudgetOrdinance2432
P. 163

CITY OF EULESS
                                                    CAPITAL  IMPROVEMENT  PROGRAM
                                                   AMENDMENTS --   FUNDED PROJECTS
             PROJECT#            PROJECT  DESCRIPTION          DATE                  MENDMENTS &   ACTIONS
             AC1901  Texas Star Sports Complex Phase VII     05/ 31/ 2025 To decrease budget by 4, 811 for arbitrage payment.
             CM0804   Redevelopment                          10/ 01/ 2024 To provide additional funding per FY2025 Approved CIP Plan — $ 1, 000, 000
                                                                     from Car Rental Fund.
             CM0804  Redevelopment                           05/ 31/ 2025 To increase funding for earned interest of $79, 417.
             DR1101  Flooding Mitigation                     10/ 01/ 2024 To transfer excess funding  per FY2025 Approved  CIP Plan — $  160, 000  to
                                                                     Drainage CIP Fund Balance.
             DR2501  Carr Park Creek Erosion Protection      10/ 01/ 2024 To provide  funding  per FY2025  Approved  CIP Plan — $  105, 000 from
                                                                     Drainage CIP Fund Balance.
             DR2502  FY2025 Drainage Curb &  Gutter Improvements  10/ 01/ 2024 To provide  funding  per FY2025 Approved  CIP Plan — $  265,000 from
                                                                     Drainage Operating Fund.
             DR2502  FY2025 Drainage Curb &  Gutter Improvements  05/ 31/ 2025 To close project.
             DR2503  South Mills Drive Outfall Restoration   10/ 01/ 2024 To  provide  funding  per  FY2025  Approved  CIP  Plan — $  55, 000  from
                                                                     Drainage CIP Fund Balance.
             DV9901  EDC  Incentive  Funds                   10/ 01/ 2024  To provide additional funding per FY2025 Approved  CIP Plan — $ 25, 000
                                                                     from EDC Operating Fund.
             FM1201  ADA/ TAS Facility Improvements          10/ 01/ 2024  To provide additional  funding per FY2025 Approved  CIP Plan — $ 15, 000
                                                                     from Car Rental CIP Fund Balance.
             FM2311  Fire Station #2                         05/ 31/ 2025  To increase funding for earned interest of $ 162, 379.
             FM2312  Police &  Courts Building Remodel       05/ 31/ 2025  To increase funding for earned interest of $ 1, 161, 555.
             F M 2409  Animal Shelter Expansion/ Renovation  10/ 01/ 2024  To provide additional  funding  per FY2025 Approved  CIP Plan — $ 150,000
                                                                     from Car Rental  Fund.
             FM2508  Facility Renovations  at 1400 South Pipeline  Road  10/ 01/ 2024  To provide  funding  per FY2025 Approved  CIP Plan — $ 1, 500, 000 from Car
                                                                     Rental Fund and $ 1, 500, 000 from Dallas Stars Contribution.
             FM2508  Facility Renovations at 1400 South Pipeline Road  06/ 10/ 2025  To provide additional funding per City Council Authorization — $ 100,000
                                                                     from Car Rental  Fund and $ 100, 000 from  Dallas Stars Contribution.
             GC1801  TSGC Miscellaneous Improvements         10/ 01/ 2024  To provide additional funding per FY2025 Approved  CIP Plan — $ 75, 000
                                                                     from TSGC  Reserve  Fund.
             GC2501  Golf Course Upgrades                    10/ 01/ 2024  To provide funding per FY2025 Approved  CIP Plan — $ 2, 140, 000 from Car
                                                                     Rental Fund.
             GC2501  Golf Course Upgrades                    06/ 24/ 2025  To provide  additional  funding  per City Council Authorization — $  50, 000
                                                                     from Hotel/ Motel Fund and $ 50, 000 from Car Rental Fund.
             PR0720  Miscellaneous  Park Improvements        10/ 01/ 2024  To provide additional  funding  per FY2025 Approved  CIP Plan — $ 200, 000
                                                                     from EDC Operating Fund.
             PR0804  Park Irrigation                         10/ 01/ 2024  To provide  additional  funding  per FY2025 Approved  CIP Plan — $ 25, 000
                                                                     from EDC Operating Fund.
             PR2011  Wilshire  Park Upgrades                 05/ 31/ 2025  To close project and transfer  excess funding  of $ 703 to EDC CIP Fund
                                                                     Balance.
             PR2203  Blessing Branch Park Improvements       05/ 31/ 2025 To close project and transfer excess funding of $ 32, 054 to EDC CIP Fund
                                                                     Balance.
             PR2404  Parks at Texas Star Lighting Upgrade    05/ 31/ 2025 To close project.
             PR2508  Parks at Texas Star South  Improvements  10/ 01/ 2024 To provide  funding  per FY2025 Approved  CIP Plan  750, 000 from  EDC
                                                                     Operating Fund.
             PR2509  Parks at Texas Star South Turf—  Fenway/ Shea/ Jacobs Fields  10/ 01/ 2024 To provide  funding  per FY2025 Approved  CIP Plan  258, 200 from  EDC
                                                                     Operating Fund.
             PR2509  Parks at Texas Star South Turf — Fenway/ Shea/ Jacobs Fields  05/ 31/ 2025 To close project.
             PR2510  Playground Shade Structures             10/ 01/ 2024 To provide funding per FY2025 Approved  CIP Plan  950, 000 from EDC
                                                                     Operating  Fund.
             P51902  FY2019 Street Reconstruction — Pipeline/ Highland/ Harwood  10/ 01/ 2024  To provide additional  funding per FY2025 Approved  CIP Plan — $ 1, 000,00C
                                                                     from  Federal  Appropriations  Grant.
             PS1902  FY2019 Street Reconstruction — Pipeline/ Highland/ Harwood  05/ 31/ 2025  To increase funding for earned interest of $290, 083.
             PS1903  Miscellaneous  Screening  Wall Repair   10/ 01/ 2024  To provide  additional  funding  per FY2025  Approved  CIP Plan — $ 25, 000
                                                                     from General Fund.
             PS2202  Mid- Cities/ Cheek- Sparger &  SH 121 Intersection/ ADA Imp.   05/ 31/ 2025  To close project.
                     Design
             PS2401  FY2024 Street Improvements              05/ 31/ 2025 To close project.
             PS2501  Fuller - Wiser Road/ Bear Creek Parkway  Roadway  10/ 01/ 2024 To provide funding  per FY2025 Approved  CIP Plan — $ 165, 000 from  Street
                     Rehabilitation                                  CIP Fund Balance.
             PS2502  FY2025 Street Improvements              10/ 01/ 2024 To provide  funding  per FY2025  Approved  CIP  Plan — $  1, 125, 000 from
                                                                     General Fund.
             WT0104  Well Repairs                            10/ 01/ 2024 To provide  additional  funding  per FY2025 Approved  CIP Plan — $  50, 000
                                                                     from W/ WW Operating Fund.
             WT0803  Meters/ Transponders/ Leak Detection    10/ 01/ 2024 To provide additional funding per FY2025 Approved  CIP Plan — $ 158,000
                                                                     from W/ WW Operating Fund.



                Ordinance No.  2432,  Page 157 of 474
                                                              3
   158   159   160   161   162   163   164   165   166   167   168