Page 31 - CityofArlingtonFY26AdoptedBudget
P. 31
Business Plan
Enhance Mobility
Plan, Manage, and Maintain Public Infrastructure
Project Performance Measure(s) Department(s)
Street Rebuild Projects Overall Satisfaction with the Management of Public Works
Traffic Flow During Peak Hours
Summary: Lane
Capital street projects are funded with General Roadway Capital Improvements Project Miles
Obligation (GO) Bonds and are funded through Dr. MLK Jr. Dr. (Bardin Rd. to Green Oaks Blvd) 4.02
inclusion in the annual capital budget. Mansfield Webb Rd. (Silo Rd. to Collins St.) 2.6
Mitchell St. (Collins St. to Sunnyvale Dr.) 0.8
The projects listed below include carry-over Park Row Drive (New York Ave to SH-360) 4.9
projects funded in prior years that have not Sherry Street (Park Row Dr. to Pioneer Pkwy (Spur 2.3
completed construction, as well as the planned FY 303)
2026 projects. Project milestones listed in the table
will be updated as they occur during the year.
Estimated Actual Estimated Actual
Roadway Capital Improvement Project
Bid Date Bid Date Completion Completion
Dr. MLK Jr. Dr. (Bardin Rd. to Green Oaks Blvd.) Nov. 2023 Oct. 2024 Nov. 2024
Mansfield Webb Rd. (Silo Rd. to Collins St.) Feb. 2024
Mitchell St. (Collins St. to Sunnyvale Dr.) Feb. 2024 Mar. 2025 Apr. 2026
Park Row (New York Ave to SH 360) May 2029
Sherry Street (Park Row Dr to Pioneer Pkwy May 2029
(Spur 303)
FY 2026 Proposed Budget and Business Plan 25 City of Arlington, Texas