CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                        TOTAL ALL
               PROJECT     PRIOR YEARS  FY 2023-24  FY 2024-25  FY 2025-26  FY 2026-27  FY 2027-28  FY 2028-29
                                                                                                         YEARS

                                                      STREET SYSTEM



                                                Future Street Reconstruction Projects
            Street Maintenance                              2,345,414           2,345,414           2,345,414           2,345,414           2,345,414   $      11,727,070
                 Fund
             TOTAL PROJECT   $                      -   $                     -   $        2,345,414   $      2,345,414   $      2,345,414   $      2,345,414   $      2,345,414   $      11,727,070

             IMPACT ON O&M  The project is capital maintenance of streets and minimal operating impact is anticipated.

                                                    2024 Street Reconstruction
            Street Maintenance                  2,345,414                                               $        2,345,414
                 Fund
             TOTAL PROJECT   $                      -   $       2,345,414   $                       -   $                    -   $                     -   $                     -   $                     -   $        2,345,414
             IMPACT ON O&M  The project funds utility relocations for street projects and minimal operating impact is anticipated.


                                                     2020 Utility Relocations
             Water-Wastewater                126,360                                                    $           126,360
                 Fund
             TOTAL PROJECT   $          126,360   $                     -   $                       -   $                    -   $                     -   $                     -   $                     -   $           126,360
             IMPACT ON O&M  The project funds utility relocations for street projects and minimal operating impact is anticipated.


                                                     2021 Utility Relocations
             Water-Wastewater
                 Fund                   165,000                                                         $           165,000
             TOTAL PROJECT   $          165,000   $                     -   $                       -   $                    -   $                     -   $                     -   $                     -   $           165,000
             IMPACT ON O&M  The project funds utility relocations for street projects and minimal operating impact is anticipated.


                                                   Old Town Keller E. /Bates St.
              General Fund            4,000,000               580,000                                   $        4,580,000
              Debt Issuance            5,000,000          10,000,000                                    $      15,000,000
               KDC Fund                 685,000                                                         $           685,000

                 Other                                      7,590,000                                   $        7,590,000
             TOTAL PROJECT   $       9,685,000   $     10,580,000   $        7,590,000   $                    -   $                     -   $                     -   $                     -   $      27,855,000
                          The project improves street and related infrastructure on the east side of Old Town Keller and Elm Street. The project includes a pedestrian
                          crossing on 377 and a park on Bates street. The operating impact is related to the estimated annual debt payment.
             IMPACT ON O&M
                                                  $        1,669,296   $      1,668,550   $      1,669,650   $      1,165,875   $      1,165,875