GOAL 4
Implement the city's Capital Improvement Program to improve the quality of life
for residents through the completion of projects identified in the city’s master
plans.
Responsible
Action Target Date
Department
Complete the construction of Lakewood
Boulevard to FM 1902 to serve the city's Fourth Quarter
2.4.1 Capital Engineering
future Hooper Business Park and (July - Sept 2025)
Chisholm Summit Development
Finalize design and complete
2.4.2 construction of the FY 24-25 Capital Engineering Fourth Quarter
(July - Sept 2025)
Neighborhood Street Program
Third Quarter
Begin construction for bridge connecting
2.4.3 Capital Engineering (April - June
Alsbury Boulevard to CR1020
2024)
Complete design for Alsbury Boulevard Fourth Quarter
2.4.4 Capital Engineering
extension to Lakewood Drive (July - Sept 2025)
Complete design of Hulen Street Fourth Quarter
2.4.5 Capital Engineering
expansion from SH174 to Candler Drive (July - Sept 2025)
Finalize design and begin construction of Second Quarter
2.4.6 the Burleson Police Headquarters Capital Engineering (January - March
Expansion 2025)