Infrastructure
Goal 2: Support and Expand Programs to Reduce Environmental Impacts
Objective 1: Mitigate Operating Costs and Impact on Environment
Project Performance Measure(s) Department(s)
Core Advanced Metering Install 10,000 meters and MIUs in FY 2025 Water Utilities
INF Infrastructure
2.1.1
Summary:
Estimated Actual
Milestone
The City of Arlington Water Utilities will install 10,000 Completion Completion
meters and MIU’s in FY 2025 through an ongoing meter Begin MUI/Meter Installs Oct. 2024
replacement program and water line renewals. 2024-25
Council Approval of Meter Feb. 2025
The MIU receives input from the meter register and Replacement funding
remotely sends data to a fixed base data collector, located Council Approval of Mar. 2025
at one of five elevated storage tanks around the City. Top Annual Meter Supply
of the hour readings and other diagnostics are instantly Contract
forwarded to the network allowing for a greater Complete MIU/Meter Sept. 2025
awareness of the distribution system and possible on Installation for FY 2025
property leak conditions. In addition, the MIU stores up to
35 days of hourly consumption, providing the utility with
the ability to extract detailed usage profiles for consumer
education, such as water conservation, and billing dispute
resolution.
Infrastructure
Goal 2: Support and Expand Programs to Reduce Environmental Impacts
Objective 1: Mitigate Operating Costs and Impact on Environment
Project Performance Measure(s) Department(s)
Core Water Conservation Program Maintain metered ratio rolling Water Utilities
INF average above 88%
2.1.2
Summary:
The City of Arlington Water Utilities will maintain a Metered Ratio
metered ratio rolling average above 88%. In FY 2025,
Arlington Water Utilities will proactively evaluate 25,000 100%
linear feet of water line for leaks to catch them in the
80%
early stages before significant water loss occurs.
Arlington Water Utilities will also evaluate and make 60%
recommendations to purchase additional leak detection
technologies to accomplish this goal. 40%
20%
0%
FY 2025 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr
Total