                                                    Infrastructure


                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                          Project                     Performance Measure(s)                Department(s)
             Core   Public Works South          •  Overall Satisfaction of Project   Asset Management
             INF    Operations Facility           Management
             1.2.7                              •  Project Completion on Time and at
                                                  Budget
             Summary:

             The City’s South Service Center at 1100 SW Green Oaks
             Blvd. includes administrative and customer services offices
             for Water Utilities, field offices for Public Works, site for
             materials storage and heavy equipment, as well as a fleet
             shop. The site is about 25.5 acres.

             In May 2023, voters approved $9 million to build a new
             facility for PW field operations. The existing facility is 6
             modular buildings combined into one in 2007 to provide
             temporary size. The facility is undersized for staff and
             onsite operations. Also, the exterior includes uncovered
             materials and waste storage that requires significant
             maintenance to remain in compliance with state
             environmental regulations. The goal is to design and build
             a 13,000 square foot facility for nearly 75 field personnel
             and another nearly 70,000 square feet to accommodate
             employee parking, equipment parking, covered materials
             storage, among other additions to facilitate operations.
             Additionally, Water Utilities is assessing the site for needed
             improvements.

             City staff plan to develop and issue a Request for
             Qualifications for an architectural/engineering firm by the
              st
             1  quarter of FY 2025 to create a comprehensive scope of
             work. Consideration will need to be given to soil
             conditions, the need for a detention pond, and space for a
             future water tower on the southern side of the property
             along Nathan Lowe Dr. An estimated timeline is to be
             determined.