Page 70 - CityofMansfieldFY24Budget
P. 70

Summary of Utility Construction Projects


                   Note: costs include the expected collection of impact fees and may vary from amounts
                   borrowed depending upon the anticipated collection of impact fees.

                   FY 2024 - $54,850,000

                       •  16” Water Line - SH 360
                       •  30” Lone Star Phase II
                       •  Water Treatment Plant Expansion
                       •  12” Water Line - US 287
                       •  Miscellaneous Utilities for Roadway Projects

                   FY 2025 - $48,000,000

                       •  Watson Branch Sewer Line – US 287
                       •  Lone Star Elevated Storage Tank (design)
                       •  12/16” Water Line along US 287
                       •  42” Walnut Creek Sewer Line (design)
                       •  12” Water Line along N. Main Street (design)

                   FY 2026 - $17,807,000

                       •  Lone Star Elevated Storage Tank (construction)
                       •  12” Water Line along N. Main Street (construction)
                       •  16” Water Line along Britton Road (design)
                       •  24” Water Line along US 287
                       •  12” Water Line along Turner Warnell Road
                       •  Upper Pressure Plain Water Lines

                   FY 2027 - $18,719,800

                       •  42” Walnut Creek Sewer Line (construction)
                       •  16” Water Line along Britton Road (construction)
                       •  12” Sewer Main near Magnolia Street
                       •  12” Water Line near northern city limits
                       •  20” Water Line along US Highway 287
                       •  36” Sewer Main along Walnut Creek










                                                                                                       70