Page 345 - FY 24 Budget Forecast at Adoption.xlsx
P. 345

CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY


                                                           FISCAL YEARS
                                                                                                       TOTAL ALL
                 PROJECT    PRIOR YEARS  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26  FY 2026-27  FY 2027-28
                                                                                                        YEARS
                                                   WASTEWATER SYSTEM


                                                     Shady Hollow Lift Station
              Water-Wastewater                 140,000                                                $           140,000
                  Fund
              TOTAL PROJECT   $           140,000   $                      -   $                       -   $                     -   $                     -   $                      -   $                      -   $           140,000
               IMPACT ON O&M  The project repairs an existing lift station and minimal operating impact is anticipated.


                                                   US 377 Sanitary Sewer Project
              Water-Wastewater                 600,000                                                $           600,000
                  Fund
                  Other                   850,000                                                     $           850,000
              TOTAL PROJECT   $        1,450,000   $                      -   $                       -   $                     -   $                     -   $                      -   $                      -   $        1,450,000
                            The project relates to new wastewater lines along US 377.  Minimal operating impact is anticipated and can be absorbed within the current
             IMPACT ON O&M  budget.

                                                Annual Wastewater Line Replacements
              Water-Wastewater              1,401,538               200,000                200,000             200,000              200,000              200,000               200,000   $        2,601,538
                  Fund
              TOTAL PROJECT   $        1,401,538   $          200,000   $           200,000   $        200,000   $         200,000   $         200,000   $          200,000   $        2,601,538
               IMPACT ON O&M  The project replaces existing wastewater lines and minimal operating impact is anticipated.


                                              Big Bear West Interceptor Line Replacement
              Water-Wastewater                 575,000                                                $           575,000
                  Fund
              TOTAL PROJECT   $           575,000   $                      -   $                       -   $                     -   $                     -   $                      -   $                      -   $           575,000
               IMPACT ON O&M  The project replaces existing wastewater lines and minimal operating impact is anticipated.


                                            Cade Branch Wastewater Capacity Improvements
              Wastewater Impact              3,361,800                                                $        3,361,800
                  Fees
              TOTAL PROJECT   $        3,361,800   $                      -   $                       -   $                     -   $                     -   $                      -   $                      -   $        3,361,800
                            The project replaces existing wastewater lines and minimal operating impact is anticipated.
               IMPACT ON O&M
                                                                                    -                          -                           -                           -


                                                 Florence Lane Sewer Improvements
              Water-Wastewater                   19,000               340,415                         $           359,415
                  Fund
              TOTAL PROJECT   $             19,000   $          340,415   $                       -   $                     -   $                     -   $                      -   $                      -   $           359,415
                            The project provides a small sewer extension and related operational costs can be absorbed in the current budget.
               IMPACT ON O&M
                                                                                    -                          -                           -                           -


                                       Big Bear Central Wastewater Capacity Improvements 8" to 12"
                Debt Issuance                                          529,000                        $           529,000
              TOTAL PROJECT   $                       -   $                      -   $                       -   $        529,000   $                     -   $                      -   $                      -   $           529,000
                            The project improves existing wastewater lines and the operating impact relates to the average annual debt payment.
               IMPACT ON O&M
                                                                                    -                          -                           -                           -
                                                             343