CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY


                                                           FISCAL YEARS
                                                                                                       TOTAL ALL
                 PROJECT    PRIOR YEARS  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26  FY 2026-27  FY 2027-28
                                                                                                        YEARS
                                                      WATER SYSTEM



                                                       MSC Improvements
              Water-Wastewater                 100,000                 100,000                        $           200,000
                  Fund
              TOTAL PROJECT   $           100,000   $                      -   $                       -   $        100,000   $                     -   $                      -   $                      -   $           200,000
               IMPACT ON O&M  The project is capital maintenance of an existing facility and minimal operating impact is anticipated.


                                                       Pump Station Rehab
                Debt Issuance                                                            4,500,000    $        4,500,000
              TOTAL PROJECT   $                       -   $                      -   $                       -   $                     -   $                     -   $      4,500,000   $                      -   $        4,500,000
                            The project is capital maintenance of an existing facility and the operating impact relates to the average annual debt payment.
               IMPACT ON O&M
                                                                                            $345,943.00


                                                       SCADA Maintenance
              Water-Wastewater                 540,000                                                $           540,000
                  Fund
              TOTAL PROJECT   $           540,000   $                      -   $                       -   $                     -   $                     -   $                      -   $                      -   $           540,000
               IMPACT ON O&M  The project is capital replacement of an existing equipment and minimal operating impact is anticipated.


                                                        Knox Tank Mixer
              Water-Wastewater                 600,000              (297,002)                         $           302,998
                  Fund
              TOTAL PROJECT   $           600,000   $        (297,002)  $                       -   $                     -   $                     -   $                      -   $                      -   $           302,998
               IMPACT ON O&M  The project is capital maintenance of an existing facility and minimal operating impact is anticipated.


                                                  Pearson Pump Station Generator
                  Other                2,000,000                                                      $        2,000,000
              TOTAL PROJECT   $        2,000,000   $                      -   $                       -   $                     -   $                     -   $                      -   $                      -   $        2,000,000
               IMPACT ON O&M  The project is capital maintenance of an existing facility and minimal operating impact is anticipated.

                                                  Bates Street Line Replacements
                  Other                   675,000                                                     $           675,000
              TOTAL PROJECT   $           675,000   $                      -   $                       -   $                     -   $                     -   $                      -   $                      -   $           675,000
               IMPACT ON O&M  The project replaces existing water lines and minimal operating impact is anticipated.