Page 142 - GrapevineFY24 Adopted Budget
P. 142
Project Name: Water Utility
Responsible Department: Public Works
Location: Water Treatment and Wastewater
Treatment plants
Total five-year estimated cost: $20,000,000
Funding Source: Certificate of Obligation
Description: Project will renovate and expand
the city’s water treatment and wastewater treatment administrative buildings. At the water
treatment plant, the filter building will be expanded along with the addition of a storage and
maintenance building. Within the facility, restrooms and lockers will be enhanced to support staff
and a dedicated laboratory and control room will be added.
At the wastewater plant, a new building will be constructed along with a new vehicle maintenance
facility and other site improvements.
Project Name: Municipal Service Center
Responsible Department: Multiple
Location: 501 Shady Brook Dr.
Total five-year estimated cost: $10,000,000
Funding Source: Multiple
Description: Damaged in December 2022 by a
tornado, this project encompasses repair and
renovation of the City’s Municipal Service Center.
Repairs to the roof were completed in 2023 and
now work shifts to renovating the interior to meet building code and ADA requirements.
Renovations will include the addition of an elevator, two new enclosed stairs, upgrades to all major
mechanical, electrical, and plumbing systems, and updates to staff areas. Additional enhancements
are planned for parking areas, a materials storage area, fueling station, and loading dock.
Renovations are expected to be completed in spring 2025.
142