Page 199 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 199

PROJECT TITLE:  MIDWAY PARK PICKLEBALL      COURTS                         PROJECT CODE:  PR2308

           NET  EFFECTS  ON  OPERATING   AND                    TOTAL  ESTIMATED   CAPITAL  COST:
           MAINTENANCE    COST (+   OR -)  ANNUAL:

           Direct Operatina Cost                                Site Preparation                           7, 500

           Personnel:       Full Time                           Concrete Work                             70, 794
                            Part Time                         0 Light System                              16, 450
           Total Salary                                       0 Paddle Sets                                  250
           Purchase of Services                                 Net Poles,  Nets,  and Cranks              1, 328

           Materials &  Supplies                                Sport Court Surface                       57, 658
           Utilities                                            Black Chain Link 8'                       22, 230
                                                                Windscreen  6'                             4, 514
                                                                Labor                                      7, 067
                                                                Freight                                    3, 179
                                                              0 5%  Contingency                            9, 550
           Subtotal:                                          0 Total Estimated Capital Cost             200, 520

           Maintenance  Costs                                   Funding Source:
                                                                Transfer  from:
                                                                EDC Operating Fund                       200, 520


                                                              0

           Subtotal:                                          0




           Total Estimated Annual Cost $                      0 Total Funding $                          200, 520
                                                   CURRENT     STATUS
                                                                               OVER/ UNDER
           PHASE/ FUNDING  SOURCE                      BUDGET      EXPENDED     BUDGET (-+) %         EXPENDED
          Construction $                                200, 520 $    193, 805 $       6, 715              97%






















           TOTAL  PROJECT                               200, 520 $    193, 805         6, 715              97%



                Ordinance No.  2360,  Page 199 of 326