PROJECT TITLE:  BLESSING BRANCH PARK IMPROVEMENTS                          PROJECT CODE:  PR2203

           NET EFFECTS ON OPERATING      AND                    TOTAL  ESTIMATED   CAPITAL  COST:
           MAINTENANCE    COST (+   OR -)  ANNUAL:

           Direct Operatina Cost                                Approximately 28, 000 sq ft of

           Personnel:       Full Time                           4" x8'  concrete  trail $                158, 480
                            Part Time $                       0 Playground/  Border $                     60, 000
           Total Salary $                                     0 Picnic pads w/grills                      20, 000
           Purchase of Services                                 Shade shelter/pavilion/ gazebo            30, 000

           Materials &  Supplies                                Trail Lighting                            50, 000
           Utilities                                            Playground  chips                          5, 400
                                                                Design/ Survey/Engineering                23, 800
                                                                Contingency                               17, 384


                                                              0
           Subtotal: $                                        0 Total Estimated Capital Cost             365, 064

           Maintenance  Costs                                   Funding Source:
                                                                Transfer  from:
                                                                EDC Operating Fund                       365, 064


                                                              0

           Subtotal: $                                        0




           Total Estimated Annual Cost                        0 Total Funding                            365, 064
                                                   CURRENT     STATUS
                                                                               OVER/ UNDER
           PHASE/ FUNDING  SOURCE                      BUDGET      EXPENDED     BUDGET (-+)           EXPENDED
          Engineering                                    23, 800 $     14, 550         9, 250              61 %
          Contingency                                    17, 384 $          0         17, 384               0%
          Trail Construction                            198, 480 $    195, 466         3, 014              98%
          Lighting                                       50, 000 $          0         50, 000               0%
          Park Furnishings                               75, 400 $     57, 853        17, 547              77%














           TOTAL  PROJECT                               365, 064 $    267, 870        97, 194              73%



                Ordinance No.  2360,  Page 195 of 326