                                            Capital Project Request


                                                                                                    April  30,  2019
           Department:            TEXAS  STAR  GOLF  COURSE                    Date  Prepared:
           Submitted By:          GLENDA  HARTSELL-  SHELTON                   Date  Completed:
           Project  Title:        TEXAS STAR SLOPE WALL PROTECTION        PHASE I
           Project  Type:         DRAINAGE                    Sub - Type:   IMPROVEMENTS

           Project Code:          GC2003                      Priority:   A
           COUNCIL  AUTHORIZATION:
           August 3,  2020:  Awarded Bid No.  013- 20 for Channel Improvements at the Texas Star Golf Course ( TSGC),
            Hole No.  9,  and authorized  the City Manager to execute a construction  contract with Knight Erosion Control,  Inc.
           The estimated expenditure is $ 124, 771. 28.
            September 8,  2020:  Awarded Bid No.  016- 20 for Channel Improvements at the Texas Star Golf Course,  Hole
            No.  9,  and authorized  the City Manager to execute a construction  contract with Knight Erosion Control,  Inc.  The
            estimated  expenditure  is $ 129, 970.
            June  22,  2021:   Ratified City Manager action to proceed with emergency  repairs to City property along Hurricane
            Creek at TSGC.  Knight Erosion Control,  Inc.  performed  the work and the estimated  expenditure  is $ 74, 923.
           April  11,  2023:   Awarded  Bid  No.  011- 23 for channel  improvements  at the Texas  Star  Golf Course  to R. C.
            Retaining  Walls,  Inc.  The estimated expenditure  is $ 130, 751. 36 with an owner -controlled  contingency  of five
            percent of the contractual  amount and will be paid from DR9903 and GC2003.














           RELATIONSHIP   TO OTHER PROJECTS AND/ OR MASTER PLAN:






           PROJECT   DESCRIPTION:
            Project scope includes the materials and labor for the installation of slope wall protection at the pedestrian and
            cart bridges at Texas Star Golf Course on hole # 9,  along the banks of Hurricane Creek.





           PROJECT   SCHEDULE:
            Began Construction:  September 2020
            Construction Substantially Completed:  September 2021



           JUSTIFICATION:
            Continued deterioration of creek embankment could threaten the structural integrity of the bridge structures and
           the ability to navigate the cart path.