           Department:            FLEET &   FACILITY OPERATIONS                Date  Prepared:
           Submitted By:          KYLE MCADAMS                                 Date Completed:
           Project  Title:        FY2022 ROOF REPAIRS &  PREVENTATIVE      MAINTENANCE
           Project  Type:         FACILITIES                  Sub -Type:   ROOF  REPLACEMENT/  PM

           Project Code:          FM2207                      Priority:   A
           COUNCIL  AUTHORIZATION:
            December 14,  2021:  Awarded RFP No.  003- 22 for roof inspection and assessment services to Bluefin,  LLC a
            division of Mantis Innovation.










           RELATIONSHIP   TO OTHER PROJECTS AND/ OR MASTER PLAN:
            Facility Maintenance,  in conjunction with Mantis/ Blue Innovation,  conducted a full roof assessment on 29 city -
           owned facilities to determine the condition of existing roof structures.  The study established a Roof Assessment
            Maintenance Program ( RAMP)  for City buildings.  The assessment also identified at what point in the future the
            roofs would likely need repairs,  restoration,  or full replacement.  The facilities previously identified in this project
           were part of the assessment  project.




           PROJECT   DESCRIPTION:
           As a result of the assessment, full replacement of the roof on the finance building is no longer necessary and
            modification of the project scope significantly reduces estimated costs.  The assessment determined that
            implementation of a comprehensive preventative maintenance plan combined with general roof repairs such as
           drain repairs,  removal of accumulated debris,  repairs to edge caps,  and general resealing of flashings,  curb
            boxes, and gas/ electric service entrances were sufficient to extend the useful life of many of the roofs.  As such,
            project funding has been reallocated to address these needs.




           PROJECT SCHEDULE:
            Summer  2023










           JUSTIFICATION:
           The roof assessment conducted in early Spring of 2022 identified structures in need of immediate attention.
           These structures were categorized as Roof Preventative  Maintenance to extend the lives of the roofs or as Roof
            Repairs to address potential leaks.  The proposed preventative maintenance and general repairs suggested for
            City structures will extend the useful lives of the roofs and defer complete replacement/ restoration into the future.






                Ordinance No.  2360,  Page 178 of 326