Page 119 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 119

PROJECT TITLE:  LINE REPLACEMENT —  TRAILWOOD ADDITION                     PROJECT CODE:  WW2304

           NET EFFECTS ON OPERATING      AND                    TOTAL  ESTIMATED   CAPITAL  COST:
           MAINTENANCE    COST (+   OR -)  ANNUAL:

           Direct Operatina Cost                                Engineering $                            607, 000

           Personnel:       Full Time                           Construction $                         2, 781, 934
                            Part Time $                       0
           Total Salary $                                     0
           Purchase of Services

           Materials &  Supplies
           Utilities






                                                              0
           Subtotal:                                          0 Total Estimated Capital Cost           3, 388, 934

           Maintenance  Costs                                   Funding Source:
                                                                Transfer  from:
                                                                W/WW Operating Fund                      607, 000
                                                                American Rescue Plan Act               2, 429, 000
                                                              0

           Subtotal:                                          0 Additional Funding Needed:
                                                                Transfer  from:
                                                                American Rescue Plan Act                 352, 934
           Total Estimated Annual Cost                        0 Total Funding                          3, 388, 934
                                                   CURRENT     STATUS
                                                                               OVER/ UNDER
           PHASE/ FUNDING  SOURCE                      BUDGET      EXPENDED     BUDGET (-+)           EXPENDED
          Engineering                                   607, 000 $    150, 531 $    456, 469               25%
          Construction                                2, 781, 934 $         0 $    2, 781, 934              0%




















           TOTAL  PROJECT $                           3, 388, 934 $   150, 531 $   3, 238, 403              4%