CAPITAL IMPROVEMENTS  PROGRAM (CIP)



        IntroductIon
        In accordance with the Texas Local Government         FY 2023 cIp calendar
        Code and the Charter of the City of Southlake, the
        FY 2023 to FY 2027 Capital Improvements Program
        (CIP) is submitted for City Council consideration.    aprIl 2022       cIp project Forms due

        The challenges to retain and/or expand City      maY 2022              cIp governance commIttee
        services in the midst of balancing resources and                       revIew
        growing costs has put pressure on City government
        to make its limited capital resources work more   june 2022            FInal cIp governance
        efficiently. City administration, elected and                          commIttee revIew
        appointed officials, and staff have taken several
        steps to make its capital expenditures more closely   julY 2022        cItY manager revIew
        reflect its long-range objectives.
                                                         august 2022           spdc / parks Board
        One such step is the connection between the City’s                     recommendatIon
        capital planning efforts with its budgeting process.                   cItY manager FIles Budget
        The CIP establishes a five year funding schedule
        for the purchase, construction, or replacement of                      cItY councIl work sessIon
        physical assets of the City.  Capital improvements
        typically have a useful life of more than ten years   septemBer 2022   cItY councIl work sessIon
        and value greater than $10,000.  The first year                        1st readIng and puBlIc
        of the Capital Improvements Program is called                          hearIng
        the Capital Budget and is appropriated in the
        same manner as the annual Operating Budget.                            cItY councIl 2nd readIng
        Funds for projects are appropriated on an annual                       and puBlIc hearIng
        basis.  Projects approved for subsequent years are
        approved for planning purposes only and do not
        receive expenditure authority until they are part of the Capital Budget.

        creatIng the capItal Improvements program

        In May 2022, the CIP Governance Committee, comprised of the Executive Leadership Team, began the process of
        evaluating CIP project requests. The methodology involved a presentation of each project by a staff member of the
        requesting department and the use of the CIP project evaluation form.

        Following presentations by each requesting department, the projects were ranked in the appropriate funding
        category (i.e. General Fund, Utility Fund, SPDC). The resulting ranked project list was then reviewed by the
        Governance Committee to ensure that there were no obvious flaws in the ranking system. The Governance
        Committee then reviewed the dollar amount available in each fund and recommended the projects to be funded in
        the upcoming fiscal year (FY 2023) and the other four future years (FY 2024 to FY 2027).

        Once the Governance Committee completed its review, the list was presented to the City Manager who then met
        with the Governance Committee regarding needed changes or additions.  The Governance Committee input revisions
        and held additional meetings with department heads as needed to ensure the proposed plan is comprehensive.


        Prior to the City Manager’s submission of the Capital Budget, the Southlake Parks Development Corporation (SPDC)
        and the Parks Board met to review and recommend their respective portions of the budget and five-year plan.









   300    FY 2023 City of Southlake  |  BUDGET BOOK