CITY OF SAGINAW
GENERAL LONG TERM DEBT SERVICE REQUIREMENTS
2022-2023
DISBURSEMENT AMOUNT DISBURSEMENT AMOUNT
2020 General Obligation Refunding Bonds 2016 General Obligation Refunding Bonds
Principal $ 105,000 Principal $ 445,000
Interest 10,212 Interest 37,434
TOTAL $ 115,212 TOTAL $ 482,434
2013 General Obligation & Refunding Bonds 2017 General Obligation Bond
Principal $ 475,000 Principal $ 340,000
Interest 202,781 Interest 189,450
TOTAL $ 677,781 TOTAL $ 529,450
2014 General Obligation Refunding Bonds 2019 Tax Note
Principal $ 230,000 Principal $ 230,000
Interest 9,154 Interest 11,480
TOTAL $ 239,154 TOTAL $ 241,480
2015 General Obligation Bonds 2019 General Obligation Refunding Bonds
Principal $ 355,000 Principal $ 425,000
Interest 153,300 Interest 10,432
TOTAL $ 508,300 TOTAL $ 435,432
2020 Certificates of Obligation 2021 General Obligation Bonds
Principal $ 100,000 Principal $ 305,000
Interest 637,700 Interest 219,000
TOTAL $ 737,700 TOTAL $ 524,000
- TOTAL REQUIREMENTS
Principal $ 415,000 Principal $ 3,425,000
Interest 1,329,063 Interest 2,810,005
TOTAL $ 1,744,063 17,000
TOTAL $ 6,252,005
Explanation of Use for Debt Obligations
• 2015 GO Bonds - Bailey Boswell Overpass Project
• 2017 GO Bonds - Next phase of Bailey Boswell Overpass Project
• 2019 Tax Note - Land purchase for Fire Station, Library, and Senior Center; these funds are also for playground and Police
Department parking lot
• 2020 Certi cates of Obligation - Sidewalk improvements, design of Knowles Dr., Fire Station design, and miscellaneous
roadway design
• 2021 GO Bonds - Design of Library and Senior Center, also funds construction of the 1st phase of Knowles Dr.
• 2022 GO Bonds - Construction of Library/Senior Center facility.
Table of Contents 175