Multi-Year Summary

                                             Drainage Construction

                                                        Budget    Budget     Budget     Budget     Budget
        Drainage Improvements                          2022-2023  2023-2024  2024-2025  2025-2026  2026-2027  Total
        Prior Year Carryover Projects                 $       176,739                                       $       176,739
        Shadow Oaks Drainage Improvements                     208,080                                               208,080


        Glen Abbey Drainage Improvements                        403,510                                               403,510

        Chapel Hill Drainage Analysis                           77,250                                                77,250

        3 Area Drainage Analysis                                  58,500                                              58,500

        Walnut Creek Country Club Flood Analysis                80,000                                                80,000


        Day Miar Road Channel ROW & Construction            1,500,000                                             1,500,000
        Hogpen Study Update                                    450,000                                                450,000

        Serenity Park Channel Stabilization                               250,000                                   250,000
        Arbors Channel Reconstruction                                     245,000                                   245,000

        Hogpen/Callendar Road Detention Pond - Design                     200,000                                   200,000

        Watson Branch Channel Design                                   2,000,000                                  2,000,000
        Service Center Building D                                         800,000                                   800,000

        Hogpen/Callendar Road Detention Pond - Construction                      1,500,000                        1,500,000
        Watson Branch Channel Construction                                       2,800,000                        2,800,000
        Hogpen/Debbie Lane Detention Pond - Design                                             300,000              300,000

        Hogpen/Debbie Lane Detention Pond - Construction                                               1,500,000        1,500,000
        Newt Patterson/Nichols Branch Crossing Reconstruction                                  500,000                500,000
        Convenience Center Design/ROW                                                                  1,000,000        1,000,000
          Total                                       $     2,954,079 $     3,495,000 $     4,300,000  $      800,000 $     2,500,000  $   14,049,079


                                     Major FY 2022-2023 Drainage Projects

               Day Miar Channel Right-of-Way and Construction - $1,500,000

               In conjunction with the Street Construction Fund, Day Miar Road is planned to be improved to a
               four-lane undivided concrete roadway.  Roadway drainage will be curb and gutter with inlets and
               piping draining to an improved parallel open channel on the west side of the road.  The open
               channel will extend from the south side of Grand Meadow Blvd. to the detention area north of
               Lake Ridge High School, and then cross to the east side of the road through an improved culvert.























                                                                                                         276