Page 244 - Project Detail Sheet_AdoptedBook
P. 244

ADOPTED | BUDGET

                                               Aquatic Park Capital Projects
                Department                                     Project Title                         Project Number
        Aquatic Park                     Waterpark Security Camera System Improvements and Upgrades      WP2102
                                                      Project Description
        This project consists of security camera system upgrades and improvements for the waterpark primarily in the areas of the parking
        lot, entryway and perimeter.  This also includes funds for hardware, cabling and other items that are necessary for the camera
        system upgrades.







                                                      Project Justification
        As the park has aged, the original perimeter camera system that was installed on a homeland security grant has begun to break
        down, become obselete and need repairs/replacements.  During this time the land next to the park has seen a vast increase in
        homes and apartments being built and this in turn has caused more fence jumping by guests as well as more people attempting to
        enter the park over night.  This project is important to help stop this as well as to assist should any potential emergency situations
        arise out of these occurences.

        Note: Project funding source is Park Sales Tax (126).











        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2020-21        $25,000
        Engineering/Design                                               Total                            $25,000
        Land/ROW Acquisition
        Construction                     10/2020         09/2021
        Other
        Total Schedule                   10/2020         09/2021
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves
        Sales Tax                         25,000              0                0               0          $25,000
        Other
        Total Funding                    $25,000             $0               $0              $0           $25,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      25,000               0               0               0           $25,000
        Other
        Total Costs                      $25,000              $0              $0              $0           $25,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0