Page 165 - Project Detail Sheet_AdoptedBook
P. 165

ADOPTED | BUDGET

                                                   Utility Capital Projects
                Department                                     Project Title                         Project Number
        Public Works                                  Large Valve Replacement Project                     UT1901
                                                      Project Description
        The Large Water Valve Replacement Project encompassed the replacement of two, 24 inch valves, a 12 inch valve, and the
        installation of a 16 inch valve.  The 24 inch valve replacements are located at the intersections of Hightower and Smithfield Road
        and Hightower and Davis Boulevard.  The 12 inch valve replacement is located at Davis Boulevard and Odell Street.  The installation
        of the 16 inch valve will be near the intersection of Glenview Drive and Dawn Drive.






                                                      Project Justification
        The replacement and installation of these large water valves will improve circulation and enhance water quality.  The completed
        project will reduce the number of residential and business connections affected by water outages, decrease the time water is off for
        repair, and greatly reduce the amount of water loss during water main breaks or construction mishaps.  These valves are located on
        large mains and are buried deep in the ground.  These are not typically valve replacements and an outside contractor with
        experience replacing valves of this size and depth will be used.

        Project Status Update: Project is currently in initial preparation phases.











        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2018-19        $95,000
        Engineering/Design                                               Total                            $95,000
        Land/ROW Acquisition
        Construction                     10/2018         09/2020
        Other
        Total Schedule                   10/2018         09/2020
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation        95,000              0                0               0          $95,000
        Federal/State Grants
        Reserves
        Sales Tax
        Other
        Total Funding                    $95,000             $0               $0              $0           $95,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      95,000               0               0               0           $95,000
        Other
        Total Costs                      $95,000              $0              $0              $0           $95,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0