Page 163 - Project Detail Sheet_AdoptedBook
P. 163

ADOPTED | BUDGET

                                                   Utility Capital Projects
                Department                                     Project Title                         Project Number
        Public Works                         Conn Pump Station Pump and Electrical Rehabilitation         UT2008
                                                      Project Description
        This project is to reconfigure existing suction header piping and pumps to meet the Hydraulic Institute standard for pipe pumping and
        to upgrade and reconfigure electrical components to meet the National Electric Code.









                                                      Project Justification
        Conn Pump Station provides potable water from the south of the city to just south of Mid-Cities Blvd. The pump station provides
        potable water and pressure to the distribution system through four pumps located on the site. Three of these pumps were replaced 6
        years ago. Staff became aware of noticeable wear and tear on the pumps through inspections and failures. Freese and Nichols
        Engineering group was hired to conduct a piping analysis to determine the cause for the premature pump issues. Through this
        analysis, Freese and Nichols was able to determine that the pump issues were caused by the net positive suction head created by
        the piping alignment on the suction side of the pumps. The suction piping has a 90 degree bend located too close to the pump on
        three of the four pumps. The analysis also shows that the electrical panels will have to be moved to correct the alignment of the
        piping and to meet clearance requirements from the National Electric Code.

        Project Status Update: Final design is currently underway.

        Funding Source: Certificates of Obligation.




        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2019-20      $1,500,000
        Engineering/Design               10/2019         05/2021     Revision              2020-21      $1,100,000
        Land/ROW Acquisition                                             Total                          $2,600,000
        Construction                     09/2021         04/2022
        Other
        Total Schedule                   10/2019         04/2022
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation      1,500,000             0                0               0        $1,500,000
        Federal/State Grants
        Reserves                        1,100,000             0                0               0        $1,100,000
        Sales Tax
        Other
        Total Funding                  $2,600,000            $0               $0              $0        $2,600,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design               329,000               0               0               0          $329,000
        Land/ROW Acquisition
        Construction                    2,271,000              0               0               0         $2,271,000
        Other
        Total Costs                    $2,600,000             $0              $0              $0         $2,600,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0