Page 163 - Project Detail Sheet_AdoptedBook
P. 163
ADOPTED | BUDGET
Utility Capital Projects
Department Project Title Project Number
Public Works Conn Pump Station Pump and Electrical Rehabilitation UT2008
Project Description
This project is to reconfigure existing suction header piping and pumps to meet the Hydraulic Institute standard for pipe pumping and
to upgrade and reconfigure electrical components to meet the National Electric Code.
Project Justification
Conn Pump Station provides potable water from the south of the city to just south of Mid-Cities Blvd. The pump station provides
potable water and pressure to the distribution system through four pumps located on the site. Three of these pumps were replaced 6
years ago. Staff became aware of noticeable wear and tear on the pumps through inspections and failures. Freese and Nichols
Engineering group was hired to conduct a piping analysis to determine the cause for the premature pump issues. Through this
analysis, Freese and Nichols was able to determine that the pump issues were caused by the net positive suction head created by
the piping alignment on the suction side of the pumps. The suction piping has a 90 degree bend located too close to the pump on
three of the four pumps. The analysis also shows that the electrical panels will have to be moved to correct the alignment of the
piping and to meet clearance requirements from the National Electric Code.
Project Status Update: Final design is currently underway.
Funding Source: Certificates of Obligation.
Project Schedule Beginning Date Ending Date History Fiscal Year Amount
Professional Services Adopted Budget 2019-20 $1,500,000
Engineering/Design 10/2019 05/2021 Revision 2020-21 $1,100,000
Land/ROW Acquisition Total $2,600,000
Construction 09/2021 04/2022
Other
Total Schedule 10/2019 04/2022
Sources of Funds Appr. To Date 2021‐22 Budget 2022‐23 Estimate 2023‐Completion Total Funding
General Obligation Bonds
Certificates of Obligation 1,500,000 0 0 0 $1,500,000
Federal/State Grants
Reserves 1,100,000 0 0 0 $1,100,000
Sales Tax
Other
Total Funding $2,600,000 $0 $0 $0 $2,600,000
Project Costs To Date 2021‐22 Budget 2022‐23 Estimate 2023‐Completion Total Cost
Professional Services
Engineering/Design 329,000 0 0 0 $329,000
Land/ROW Acquisition
Construction 2,271,000 0 0 0 $2,271,000
Other
Total Costs $2,600,000 $0 $0 $0 $2,600,000
Operating Impact
No operating impact is anticipated.
Fiscal Year 2020‐21 2021‐22 2022‐23 2023‐24 2024‐25 Total Impact
Amount $0 $0 $0 $0 $0 $0
157