Page 142 - Project Detail Sheet_AdoptedBook
P. 142

ADOPTED | BUDGET

                                                 Drainage Capital Projects
                Department                                     Project Title                         Project Number
        Public Works                            Street Drainage Improvements Project (2021-22)           DR2201
                                                      Project Description
        This project consists of addressing a portion of the numerous non-grade standing water requests Public Works receives each year
        by removing and replacing curb and gutter systems to an adequate grade that provides positive drainage along City streets. Creating
        positive drainage along streets can sometimes require drive approaches and sidewalks to be replaced as well to accommodate the
        new grade. When this project was initially approved the list of streets to be repaired was 193 locations at the cost of $640,000, the
        current list is comprised of 184 locations at the cost of $577,395. This project will be an annual project until such time as the list of
        requests is completed or until the list can be accomplished within the operating budget.



                                                      Project Justification
        The Public Works Department receives numerous citizen request for non-grade standing water problems along City streets each
        year. Requests are repaired in the order in which they are received unless the severity of the grade causes a public safety issue.
        Standing water along City streets contributes to premature deterioration of asphalt, which provides an environment for breeding
        mosquitos that may or may not be infected with the West Nile Virus and is unsightly and concerning to residents that live near by.

        Funding Source: Drainage Utility Fund Reserves (120).












        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Proposed              2021-22       $100,000
        Engineering/Design                                               Total                           $100,000
        Land/ROW Acquisition
        Construction                     10/2021         09/2022
        Other
        Total Schedule                   10/2021         09/2022
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                              0          100,000          100,000         240,000        $440,000
        Sales Tax
        Other
        Total Funding                        $0         $100,000         $100,000         $240,000        $440,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                          0           100,000         100,000         240,000         $440,000
        Other
        Total Costs                          $0          $100,000        $100,000        $240,000         $440,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0