                                                 Drainage Capital Projects
                Department                                     Project Title                         Project Number
        Public Works                                    Mackey Creek Flood Study                         DR2005
                                                      Project Description
        This project consists of creating new hydrologic and hydraulic models to provide regulatory floodplain mapping for Mackey Creek
        from upstream of Shauna Drive to Big Fossil Creek (approximately 2.4 miles). This study would also identify potential future capital
        improvement projects to reduce the size of or completely eliminate the floodplain within the study area. The original study for
        Mackey Creek was done in 1985 with the City's Master Drainage Plan.  New topographic data is available along Mackey Creek and
        new floodplain modeling techniques would be used in the study.





                                                      Project Justification
        The data current effective modeling and mapping for Mackey Creek is based on the City's 1985 Master Drainage Plan. Floodplain
        modeling and mapping technology has advanced to be able to better estimate flood risk in areas that have both above and below
        ground storm drainage conveyance systems like the upper reaches of Mackey Creek. This study would help to give a better picture
        of flood risk to residents and business owners along Mackey Creek and would also provide recommendations for capital
        improvement projects to remove/reduce the floodplain throughout the area.

        Project Status Update: Project is currently underway and anticipated to be completed during FY21.

        Funding Source: Drainage Utility Fund (120).








        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2019-20       $120,000
        Engineering/Design               03/2020         09/2021         Total                           $120,000
        Land/ROW Acquisition
        Construction
        Other
        Total Schedule                   03/2020         09/2021
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                         120,000              0                0               0         $120,000
        Sales Tax
        Other
        Total Funding                   $120,000             $0               $0              $0          $120,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design               120,000               0               0               0          $120,000
        Land/ROW Acquisition
        Construction
        Other
        Total Costs                      $120,000             $0              $0              $0          $120,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0