CITY OF HALTOM CITY ANNUAL BUDGET, FY2022                 Capital Project Funds



          Drainage Capital Fund (46)




          During FY 2003-04, the City engaged consultants to perform a drainage study.  The result of the
          study was a plan that assesses a monthly fee to each residential customer in the City.  Commercial
          interests are billed  a per square  foot charge  based upon  the square  footage of their property
          multiplied by a runoff factor.




          During  FY2004-05,  the  City  engaged  another  consulting  firm  to  assist  in  the  preparation  of  a
          Drainage Master Plan.  As a part of the analysis, floodplain maps were studied, and the existing
          drainage system was studied.  The results of the study determined that the value of needed drainage
          projects amounted to approximately $102 million.



          The FY2021 budget includes $1,855,000 for replacement of curb and gutter in conjunction with
          street reconstruction and targeted areas in the City. Major projects approved for FY2022 include:






                                     Meachum                                 $       110,000
                                     Ray Drive and Ray Court                 $       200,000
                                     McCullar Street                         $        250,000
                                     Broadway Avenue                         $       200,000
                                     Midway Road                             $        50,000
                                     Huddleston Street                       $       150,000
                                     East Ridge Dr                           $       100,000
                                     Hahn Boulevard                          $        90,000
                                     Murray Avenue                           $       100,000
                                     Field Street (Haltom to Stanley Keller)  $        35,000
                                     Voncille Street (Glenda to Earle)       $        35,000
                                     Parker Road E/W (Webster to Vicki)      $        40,000
                                     Northern Cross                          $       250,000
                                     Hadley Street                           $        45,000
                                     Storm/Drainage road extention - Northern Cross  $       100,000