Utility costs for FY22 are budgeted at $880,220 and represent an increase of $48,000 (6%) from
               the previous year’s budget.  Estimated utility expenses in FY21 were $988,645 and represent an
               increase of 39% from FY20.

                ENTERPRISE FUND         FY-2016     FY-2017     FY-2018     FY-2019     FY-2020     FY-2021
                UTILITY COSTS

                Utility Fund            $649,927    $585,866    $501,387    $457,650    $513,244    $743,155
                Golf Fund               $194,486    $237,559    $283,772    $166,240    $199,373    $245,490
                Total                   $844,413    $823,425    $785,159    $623,890    $712,617    $988,645

                Increase / (Decrease)   ($60,025)   ($20,988)   ($38,266)  ($161,269)    $88,727    $276,028
                % Change                     -7%         -2%         -5%        -21%        14%         39%



               Transfers Out are budgeted at $1.8 million and is comprised of the 7.5% administrative fee to the
               General fund ($1,694,663 from Utility and $124,370 from Golf).  Estimated expenditures in FY21
               total $1.8 million and represent a decrease of 5.3% from the previous year.

                ENTERPRISE FUND         FY-2016     FY-2017     FY-2018     FY-2019     FY-2020     FY-2021
                OPERATING TRANSFERS OUT

                Utility Fund          $1,672,193  $3,826,308  $8,003,880  $1,343,444  $1,885,149  $1,755,683
                Golf Fund                $98,831    $108,147    $107,254     $86,377    $111,463    $134,992
                Total                 $1,771,023  $3,934,456  $8,111,134  $1,429,821  $1,996,612  $1,890,675

                Increase / (Decrease)   $107,779  $2,163,432  $4,176,678 ($6,681,313)   $566,791   ($105,937)
                % Change                    6.5%      122.2%      106.2%      -82.4%       39.6%       -5.3%

                (1)  FY-2018 Includes a one-time transfer of $5,084,734 to the Water / Wastewater Capital Projects (CIP) Fund and a one-time
                (1)  transfer of $1,000,000 to the Convention and Visitors Fund

               Debt Service expenditures are budgeted at $1.1 million, a decrease of $441,000 (28%) from the
               previous  year.   Debt service expenditures are comprised of principal  and interest  payments  on
               outstanding waterworks and sewer revenue bonds, principal and interest payments on outstanding
               golf course certificates of obligation, paying agent fees, bond issuance costs, and arbitrage fees (if
               applicable).