CITY OF SAGINAW
                             CAPITAL IMPROVEMENT PROJECTS - DRAINAGE
                                                        2020-2024


             Saginaw Blvd System #3 Pre Construction
             Scope        Acquisition of easements, railroad permits and railroad inspection
             Project Cost $530,000
             Fiscal Year  Future CIP
                          This project improves the drainage along Saginaw Blvd between McLeroy Blvd and Longhorn
                          Blvd.  The project consists of earthen channel from FM 156 to the BNSF railroad, crossing
                          under and proceeding along the west side of the railroad.  The improvements then turn
             Description
                          westward, crossing under the Union Pacific and BNSF Railroads, and proceeding across
                          Saginaw Blvd.  A main line will extend to the north from Saginaw Blvd along the west side of
                          Saginaw Blvd to Green Ave.  Another main line will be extended to the south to Hialeah Park.
             Impact on
             Operating    There is no operating impact related to the pre-construction phase of this project.
             Budget

             Saginaw Blvd System #3 Phases 1 through 4 and TxDOT Review
             Scope        McLeroy Blvd to Longhorn Blvd
             Project Cost $6,160,000
             Fiscal Year  Future CIP

                          This project improves the drainage along Saginaw Blvd between McLeroy Blvd and Longhorn
                          Blvd.  The project consists of earthen channel from FM 156 to the BNSF railroad, crossing
                          under and proceeding along the west side of the railroad.  The improvements then turn
             Description
                          westward, crossing under the Union Pacific and BNSF Railroads, and proceeding across
                          Saginaw Blvd.  A main line will extend to the north from Saginaw Blvd along the west side of
                          Saginaw Blvd. to Green Ave.  Another main line will be extended to the south to Hialeah Park.
             Impact on    The operating impact of a closed pipe project is minimal. Upon completion of drainage
             Operating    improvements, there will be fewer emergency call outs during heavy rain events   Estimated
             Budget       operating savings is $1,575.