Page 184 - Saginaw FY21 Annual Budget
P. 184

CITY OF SAGINAW
                               CAPITAL IMPROVEMENT PROJECTS - WATER
                                                        2020-2024


              Saginaw Blvd 16" Water Line Phase 2
              Scope        Palomino across Saginaw Blvd to Samson 12" water line
              Method       bore and open-cut with pavement patch
              Project Cost $1,530,000
              Fiscal Year  Construction to begin in FY 2020-2021
                           This project will provide additional transmission capacity east of Saginaw Blvd.  This project
              Description  will connect transmission mains from Longhorn Pump Station on the west side of Saginaw
                           Blvd.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating
              Budget       infrastructure ages, estimated annual maintenance cost will be $2,863.


              FM 156 12" Water Line Phase 2
              Scope        450 feet north of Topeka Dr. to Bailey Boswell Rd.
              Method       Open-cut
              Project Cost $495,000
              Fiscal Year  Future CIP
                           This project will connect transmissions mains in Bailey Boswell with tranmission mains along
              Description  FM156.  The cost estimate assumes construction of the water line before or concurrent with
                           construction of new development.
              Impact on
              Operating    There will be an eventual increase in maintenance costs as this is a new water line.  As the
                           infrastructure ages, estimated annual maintenance cost will be $2,672.
              Budget
              Condor Trail 12" Water Line
              Scope        Dunster to Bailey Boswell Rd.
              Method       Open-cut
              Project Cost $420,000
              Fiscal Year  Future CIP
                           This project will connect transmissions mains in Bailey Boswell with Heather Ride Estates
              Description  and provide distribution for future development.  The cost estimate assumes construction of
                           the water line before or concurrent with construction of new development.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating    infrastructure ages, estimated annual maintenance cost will be $2,868.
              Budget

              Defiel Rd 8" Water Line
              Scope        Defiel Rd Cul-de-sac o Bailey Boswell Rd.
              Method       Open-cut
              Project Cost $610,000
              Fiscal Year  Future CIP
                           This project will connect dead end distribution lines along Defiel Rd. with transmission mains
                           along Bailey Boswell.  This line will provide future distribution along Defiel Rd.The cost
              Description
                           estimate assumes construction of the water line before or concurrent with construction of
                           new development.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating    infrastructure ages, estimated annual maintenance cost will be $2,737.
              Budget




                                                             181
   179   180   181   182   183   184   185   186   187   188   189