Major Capital Equipment Capital Projects
        Department                                             Project Title                         Project Number
        Library                            Purchase of 7-Bin Automated Sorting System for the Library     IT2102
        Project Description
        The Library is requesting a 7-bin Automated Sorting System.










        Project Justification
        Currently staff spends 100-200 hours per week manually checking and sorting returned library materials.  An automated system will
        eliminate the amount of physical contact with library materials as part of the check-in process which will help improve the the health
        and safety of this process for Library staff.
        Note: Project funding source is the CAREs Act Federal Grant.














        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Proposed          2020-21        $68,400
        Engineering/Design                                Total                            $68,400
        Land/ROW Acquisition
        Construction
        Other                      01/2021      02/2021
        Total Schedule             01/2021      02/2021
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants              0         68,400            0             0       $68,400
        Reserves
        Sales Tax
        Other
        Total Funding                    $0        $68,400           $0            $0       $68,400
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction
        Other                             0         68,400            0             0       $68,400
        Total Costs                       $0        $68,400          $0            $0       $68,400
        Operating Impact
        Yearly Hardware Maintenance


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                        $4,500        $4,500        $4,500        $4,500        $4,500       $22,500
        Total Operating Impact        $4,500        $4,500        $4,500        $4,500        $4,500       $22,500




                                                             255