Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                               Small Water Main Replacements (2019)                   UT1905
        Project Description
        This is an annual program that is completed by the Public Works Construction Division (407-6007).  The project replaces old 2" and
        4" water mains with 6" or larger diameter water pipes. This project provides adequate fire hydrant coverage to areas currently
        without proper coverage.  This project will provide for small water main replacement on the following streets:  Freda Lane (Pearl to
        Newman), Davis Boulevard (Woods to Bursey), Circleview Drive (Lariat to Shady Lake), Meadowbrook Drive (Royal Ridge to
        Brookridge) and Woodcreek Lane (Lariat to Riviera).





        Project Justification
        This is an annual program that is completed by the Public Works Construction Division.  The project replaces old 2" and 4" water
        mains with new 6" or larger water pipes and provides adequate fire hydrant coverage to areas currently without proper coverage.  In
        addition, this project helps to replace water lines that have deteriorated to a point where numerous water line breaks are occurring
        and keep water quality to high standard.















        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2018-19       $440,000
        Engineering/Design                                Revision          2019-20         ($4,989)
        Land/ROW Acquisition                              Total                           $435,011
        Construction               10/2018      06/2020
        Other
        Total Schedule             10/2018      06/2020
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation    435,011           0             0             0      $435,011
        Federal/State Grants
        Reserves
        Sales Tax
        Other
        Total Funding                $435,011          $0            $0            $0      $435,011
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                  435,011           0             0             0      $435,011
        Other
        Total Costs                  $435,011          $0            $0            $0      $435,011
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0