Schedule 3
                                                Utility Capital Projects
                                                   Budget Summary


       Pg.  Map                                           Project To   2020/21     2021/22     2022 To      Total
       No.  ID                                              Date       Adopted    Estimated   Completion

       Project Costs
       Continuing Projects
           1  UT2004   Big Fossil 24" Interceptor             1,255,000        0          0          0 $   1,255,000
           2  UT1801  Assess and Repair 16-inch Water Transmission Main  500,000  0       0          0 $     500,000
              UT0201  Big Fossil Creek Wastewater Outfall     1,231,604        0          0          0 $   1,231,604
           3  UT1701  College Hill Ground Storage Tank Stand Pipe  85,000      0          0          0 $     85,000
           4  UT2008  Conn Pump Station Pump and Electrical Rehabilitation  1,500,000  0  0          0 $   1,500,000
           5  UT1601  Franklin Court Sewer Addition and Gifford Connection  150,000  0    0          0 $     150,000
           6  CDBG20  Garwood Drive Sanitary Sewer (CDBG)       15,000         0          0          0 $     15,000
           7  UT1402  Johnson Pump Station Component and Infrastructure Replacements  275,000  0  0  0 $     275,000
           8  UT1901  Large Valve Replacement Project           95,000         0          0          0 $     95,000
           9  UT1902  Main / Snider / Center Utility Project   225,000         0          0          0 $     225,000
           10  UT2002  Miscellaneous Water/Sewer Main Replacement (2020)  445,000  0      0          0 $     445,000
           11  UT1404  Motor Operated Transfer Valves          730,000         0          0          0 $     730,000
              UT1703  Sanitary Sewer System Rehabilitation (Various Locations)  150,000  0  0        0 $     150,000
           12  UT1704  Sanitary Sewer System Trunk Line Rehabilitation  98,120  0         0          0 $     98,120

              UT2010  Sewer Impact Fee Project                  21,000         0          0          0 $     21,000
              UT1904  Sewer Manhole Replacement and Rehabilation Project  150,000  0      0          0 $     150,000
           13  UT1705  Small Water Main Replacements (2017)    420,000         0          0          0 $     420,000
           14  UT1905  Small Water Main Replacements (2019)    435,011         0          0          0 $     435,011
           15  UT2001  Small Water Main Replacements (2020)    440,000         0          0          0 $     440,000
              UT1906  Telemetric Water Meter Annual Maintenance (2019)  400,000  0        0          0 $     400,000
              UT2003  Telemetric Water Meter Annual Maintenance (2020)  400,000  0        0          0 $     400,000
              UT2006  Utility Risk and Resiliency Assessment   150,000         0          0          0 $     150,000
           16  UT1607  Walker Branch Interceptor Project      6,016,525        0          0          0 $   6,016,525
              UT2009  Water Impact Fee Project                  21,000         0          0          0 $     21,000
           17  UT0810  Western Center Water Facility Expansion  55,000         0          0          0 $     55,000
       Total Continuing Projects                         $   15,263,260 $      0 $        0 $        0 $   15,263,260

       New Projects
           18  UT2107  Automatic Control Valve (ACV) Replacement   0      135,000         0          0 $     135,000
           19  UT2106  College Hills Ground Storage Tank Rehabilitation  0  840,000       0          0 $     840,000
           20  CDBG21  Matson Drive Sanitary Sewer                 0       15,000         0          0 $     15,000
           21  UT2102  Miscellaneous Water/Sewer Main Replacement (2021)  0  462,453      0          0 $     462,453
              UT2105  SCADA Communication Replacement              0       75,000         0          0 $     75,000
              UT2104  Sewer Manhole Replacement and Rehabilitation Project (2021)  0  250,000  0     0 $     250,000
           22  UT2101  Small Water Main Replacements (2021)        0      462,453         0          0 $     462,453
              UT2103  Telemetric Water Meter Annual Maintenance (2021)  0  400,000        0          0 $     400,000
       Total New Projects                                $         0 $   2,639,906 $      0 $        0 $   2,639,906